
Spittal Substation
NEW SPITTAL AREA 400KV SUBSTATION AND HVDC CONVERTER STATION
What we are consulting on
At SSEN Transmission, we are committed to delivering a robust and transparent consultation process underpinned by inclusion and accessibility. As a stakeholder led business, we understand the importance of involving communities and key stakeholders throughout each stage of our development process.
During this consultation, we are presenting our approach to developing a proposed new substation at Spittal. Our consultation includes technology options, environmental considerations, site selection and maps which aim to give stakeholders and community members a better visual representation of the work on the projects to date.
This period of engagement in the development phase is vital in shaping our proposals and to do this effectively we need to capture feedback from stakeholders, harness local knowledge to identify risks in key areas of the routes and explore potential community benefit opportunities.
Based on the requirements outlined in the ESO’s Pathway to 2030 Holistic Network Design, we have developed proposals to reinforce the onshore corridor between Spittal and Beauly, via Loch Buidhe. To facilitate this connection, and others as part of the wider strategy, new additional 400kV substations and associated infrastructure is also required in these three locations. We are consulting on our preferred sites for the proposed new substation and high-voltage direct current (HVDC) converter station to be located near the existing 275kV substation at Spittal.
A converter station is a site which converts Direct Current (DC) to Alternating Current (AC) or AC to DC. AC is how our houses and businesses use electricity from the grid. High Voltage DC (HVDC) is a well-established technology that allows the efficient transmission of large quantities of electricity across long distances, with much reduced electrical losses compared with AC. It also introduces greater flexibility and resilience in the operation of the network and the management of variable outputs from renewable generation. A converter station needs to connect to a substation or switching station to access the AC network.
Our optioneering process
We follow formal internal guidance to enable us to consistently and rigorously select sites for new substations, switching stations and converter stations. Each process has a number of key stages, each increasing in detail and definition and bringing technical, environmental and cost considerations together in a way which seeks the best balance in accordance with our Transmission Network Operator’s Licence and the Electricity Act 1989.
Stage 2 – Site selection – current project stage
This stage seeks to identify an initial preferred substation site from shortlisted options, which minimise where practicable physical, environmental and amenity constraints, are likely to be acceptable to stakeholders and are viable (taking into account engineering and cost requirements). The existing assets form a crucial part of this assessment to reduce the need for additional new infrastructure.
Both the process and our preferred options are then presented to the public and statutory stakeholders for consultation. Comments on our process are critical in ensuring the preferred options are the best to be taken forward to planning. Comments are taken on board and modifications may be made to ensure comments have been accommodated where practicable. These will be presented during further pre-application consultation events to the public and statutory stakeholders.
Project Need
In order to support the wider connection of both onshore and offshore renewables promoted as part of the UK’s commitment to delivering green energy targets and the transition to a low carbon energy network, SSEN Transmission proposes the establishment of a new 400kV substation near to the existing 275/132kV Spittal substation. The new 400kV substation is needed because the current 275kV network is at capacity and no further renewable energy can be connected without significant reinforcement of the north of Scotland electricity transmission network. This new substation will connect to the existing transmission network at Spittal, allowing existing and proposed renewable generators to transmit electricity to areas of demand on the GB transmission network.
Design overview
The project will see the construction of a new 400kV substation close to the existing 275kV substation site at Spittal.
The works will comprise of:
Substation:
- Construction of a new outdoor 400kV substation complete with 400kV double busbar arrangement that is approximately 530 x 340m (AIS) or approximately 250m x 200m (GIS)*.
- Installation of 2 new super grid transformers (SGT).
- A new substation control building.
Connections:
- The site requires to be connected to the existing Spittal substation via new underground cables.
- Connection with the proposed Spittal – Loch Buidhe – Beauly 400kV OHL.
- Space provision to allow for connection of future renewable energy generation projects.
*Note designs for both Air Insulated Switchgear Substation (AIS) and Gas Insulated Switchgear Substation (GIS) are currently being considered. An AIS substation is constructed with switchgear which relies on open air components, which can require large clearance areas for operation and safety, which takes up a larger area of land than GIS. A GIS substation is constructed with switchgear with gaseous reliant components which allows operation and safety clearances to be reduced compared to AIS.
New HVDC converter and Peterhead link overview
The Spittal to Peterhead HVDC project is a 2GW link and comprises of the following:
Onshore works in Caithness:
- A new 525kV DC 2GW Bi-pole HVDC converter station with a platform of 325m x 290m to be located near the new 400kV Spittal substation.
- AC underground cable connections to the New 400kV Spittal substation.
- HVDC underground cables from the converter station to a new landfall (still to be determined).
Offshore works:
- Subsea HVDC cables across the Moray Firth to Morayshire/Aberdeenshire landfall (still to be determined).
A Joint Solution
Rather than two separate sites, it is desirable to locate both new installations on a single large site, the advantages of this would be avoidance of longer AC connecting cables and a potentially reduced visual impact from keeping all new infrastructure in one location. The disadvantages are having to find a much larger site which is relatively flat and the potential to sterilise connection routes for the proposed new OHLs. Our site selection process has considered both separate and joint site options. Our preferred combined site would have a footprint of 870m x 340m.
Key Strategic Requirements
Stage 0 - Strategic options assessment
The following key requirements were identified for the new sites:
- Proximity to the existing 275kV network to minimise the amount of new overhead lines or cabling required to connect to the network.
- Large enough to accommodate the proposed individual or joint substation/converter station footprints, together with associated landscaping, contractor compounds, access and new connection routes.
- Capacity for future connections.
- In areas which do not contain environmental designations and minimise impacts on local environmental receptors.
- Enable connection routes for the proposed new 400kV overhead lines and HVDC cables.
Stage 1 – Initial site screening
16 feasible site options were identified within a 10km search radius of the existing Spittal 275kV substation using publicly available data and multi criteria analysis (MCA) to provide high level constraints information. This allowed the team to identify areas which were too sensitive, constrained or technically challenging to construct a new site on.
Assessment of the 16 options was undertaken against the key requirements and using the Red, Amber, Green (RAG) matrix in our Site Selection Guidance. This resulted in 13 of the 16 options being discounted from further assessment based on proximity to properties, distance from existing infrastructure and ecological sensitivities. Options 7, 11 and 12 were taken forward to Stage 2.
Stage 2 – Detailed site selection
Further appraisal and comparison of the 3 shortlisted options was undertaken based on the RAG matrix criteria within our Site Selection Guidance.
Engineering considerations
Connectivity:
- Proposed new HVDC cable connecting Peterhead from Spittal in case Option 7 will require crossing of existing HVDC cable. However, it has an advantage over the high voltage alternating current (HVAC) OHL circuit connection.
- Option 11 is in proximity with existing 132kV Spittal – Mybster OHLs and existing Spittal substation. Spittal – Mybster OHLs may require to be undergrounded at sections to facilitate entry of new OHL and cable connection at 400kV Spittal substation. Option 12 has advantages with respect to the preferred route corridor for the preferred Spittal to Loch Buidhe to Beauly OHL and to avoid the crossing of existing HVDC cables.
Existing Infrastructure and Proposed Substations
Footprint requirement:
- All options performed equally against these criteria. However from adjacent land use aspects Option 12 has an advantage for potential future expansion possibility.
Hazards:
- Options 7 and 11 performed equally against these criteria due to facilities in proximity.
- Option 12 potentially has fewer underground utilities and less height difference compared to Options 7 and 11.
Ground condition:
- Option 7 will require existing forestry removal. This is also an area of potential peatland and so both peatland and forestry drainage will be required.
- Option 11 is in proximity to the A9 trunk road required possible additional stabilization and it is also in proximity to archaeology.
- Option 12 has a low risk flood area, flat ground, is in proximity to an agricultural farming field.
Woodland, Ancient Woodland and Carbon / Peatland against Proposed Substations
Construction access, operation and maintenance:
- Option 7 will require major public road improvements.
- Options 11 and 12 performed equally against these criteria being in proximity to public road A9.
Environmental considerations
Natural heritage and planning:
- All options performed equally against these criteria. Designations in the area include the Achanarras Quarry SSSI, Caithness Lochs SPA.
Environmental Designations Against Proposed Substations
Habitats
- No Groundwater Dependent Terrestrial Ecosystems (GWDTE) have been identified within any of the Options or within 250 m buffer, although there is potential for these to be present and further survey would be required to confirm.
Cultural heritage designations:
- Option 11 has the highest risk of cultural heritage impact due to close proximity of site to the Magnus Hospital and Church Scheduled Monument.
Cultural Heritage Designations Against Proposed Substations
People:
- Option 7 is highly visible from Achanarras Quarry, a nearby recreational site.
- Option 12 is visible from sections of the A9 and the nearby village Halkirk.
- Option 11 is visible by traffic on the A9.
Landscape and Visual:
- Option 7 has high potential for an adverse impact on the local landscape due to the loss of the woodland, a sparse feature of the landscape. Options 11 and 12 have some potential to impact the landscape character.
- Options 7, 11 and 12 would be partially visible from scattered settlements to the north and west of the existing substation. Options 7 and 11 would be highly visible from Achanarras Quarry, and the core path leading to it.
Land use:
- Options 7 would require the removal of commercial woodland and may affect the recreational value of the Achanarras Quarry SSSI, used by fossil hunters, due to a reduction in visual amenity.
Option 7 Substation Zone of Theoretical Visibility and Other Visual Receptors
Option 11 Substation Zone of Theoretical Visibility and Other Visual Receptors
Option 12 Substation Zone of Theoretical Visibility and Other Visual Receptors
Our preferred site
The environmentally preferred site is Option 11.
- Option 7 has the potential for more significant landscape and visual impact.
- Sites 11 and 12 are closely balanced, with Option 12 having potential for a slightly higher impact on landscape and visual receptors and Option 11 the greater potential for impact on cultural heritage due to the St Magnus Hospital and Church Scheduled Monument close to the southern site boundary.
- Of these two constraints, landscape is considered likely to be more significant and as such, Option 11 is marginally preferred.
The Engineering preferred site is Option 12 from connectivity and future connections aspects. Option 11 is also closely balanced from access aspect but future expansion would be challenging. Option 7 is more challenging compared to Options 11 and 12 due to forest cutting and peatland possibility. The preferred option is Site Option 12.
Therefore, taking these factors into consideration our overall preferred site is Option 12.
Interactive Map
Acknowledgements
© Landmark Information Group Limited and/or its Data Suppliers (All rights reserved 2010)
Contains Historic Environment Scotland and Ordnance Survey data © Historic Environment Scotland - Scottish Charity No. SC045925
Contains public sector information licensed under the Open Government Licence v3.0