South College Avenue Reconstruction Phase 1

Villa Maria Road to Carson Street

Project Overview

This project provides for the reconstruction of approximately 4,300 linear feet of South College Avenue. Improvements include:

  • Reconstruction of asphalt to concrete roadway.
  • Installation of an underground storm sewer system.
  • Replacement of aging water and sewer lines.
  • Construction of an improved box culvert creek crossing.
  • Construction of improved pedestrian facilities, including a 12-foot wide shared use path along the west side of South College Avenue and a 6-foot-wide sidewalk along the east side of South College Avenue.

Two roundabouts are proposed in this project: one at the intersection of South College Avenue and Carson Street and another at the Hollydale Street and Williamson Drive intersection.

Renderings of Hollydale Street and Williamson Drive Roundabout from Original Concept

Renderings of Carson Street Roundabout from Original Concept

Project Goals

  • Improve the safety and efficiency of this roadway for both vehicular and pedestrian traffic in the area.
  • Improve the stormwater drainage system to reduce localized flooding by upgrading the storm sewer network.
  • Replace aging infrastructure including water and sewer lines.
  • Encourage neighborhood revitalization and economic development.

Project Cost

  • Design = $ 547,455.00
  • Construction = $ 15,603,694.81


Current Construction Status

The project is currently in construction, and is 66% complete by Contract Valve and approximately 33% complete overall.

In the past three months, approximately 1,500 linear feet of roadway has been completed and is now fully drivable.

·         November 4, 2024: Opening from Villa Maria Road to Dellwood Street.

·         November 15, 2024: Opening from Dellwood Street to approximately 100 feet north of Edge Street.

·         November 22, 2024: Opening from 100 feet north of Edge Street to 100 feet south of Bizzell Street, including the Rountree Drive intersection.

·         December 20, 2024: Opening from 100 feet south of Bizzell Street to 150 feet north of Bizzell Street was completed and opened.

These openings mark critical progress in providing improved accessibility and traffic flow along the corridor.

 Upcoming Work

In January, the City of Bryan is looking forward to significant progress from Larry Young Paving (LYP). The city anticipates that LYP will continue work on South College Avenue to open another 800 feet of roadway, just short of the Hollydale/Williamson Roundabout. Simultaneously, between Carson Street and Hollydale Street, LYP will be installing storm sewer boxes in preparation for connecting the storm sewer system. Finally, weather permitting, LYP will begin work on the Hollydale/Williamson Roundabout.

 The City of Bryan will continue to oversee and coordinate with LYP to ensure the project progresses and a high-quality product is delivered. However, the timing and execution of tasks remain under Larry Young Paving’s management.

Prioritizing Roadway Opening

The City of Bryan’s priority is to open the roadway as soon as possible to improve traffic flow and accessibility. As we continue to open sections of the roadway, some sidewalks and shared-use paths may still be under construction. Consequently, Larry Young Paving (LYP) may be working on sidewalk construction and other tasks concurrently while the roadway remains open. We appreciate your understanding as we balance these efforts to minimize disruptions.

For additional information, please see the posted monthly update letters on the main website.

Overall completion of the project is estimated to be in Summer 2025.


Project Completeness Breakdown

Please note that the task categories listed under "Item Description" may include subtasks that are indirectly related but essential for overall completion. For example, waterline items include the demolition and repair of concrete pavement as necessary for the installation of the waterline.

Why is progress reported in % Complete by Contract Value and not % Complete by Schedule?

We use Percent (%) Complete by Contract Value (PCCV) because it provides a more consistent measurement across different stages of construction and the overall project. PCCV integrates Earned Value Management (EVM) practices and ensures that the work completed accurately reflects the money spent rather than how far into the schedule we are. Ideally, project completeness could be estimated by comparing days completed to the overall project schedule. However, in practice, construction is not a linear process and some tasks are disproportionate to the overall work.

For example, different phases of the project may require varying amounts of time due to unforeseen site conditions, task complexity, varying work efforts, and potential delays. Consider a building with a 12-month construction contract duration. At the 6-month mark, due to delays in site preparation and foundation work, the project has only just started superstructure construction. According to the schedule, 50% of the project contract time has elapsed, which can mislead one to assume that 50% of the work is done. However, this does not reflect the delays and additional time needed to complete the remaining work. In reality, only 25% of the work may be complete while 50% of the contract time has been used.

Additionally, when using PCCV, one should be careful to avoid assuming that costs are proportionate to the overall project completeness.

Project Delays

Given the general complexity of Capital Improvement Projects (CIPs), which often involve decades long master planning, unforeseen site conditions, and coordination between numerous regulatory and private entities, delays in project progress are always possible. This has certainly been the case with the South College Avenue Reconstruction Phase 1 project. For context, we’ve provided a brief description of the major delays below.

Telecoms Relocations

  • Before the city’s contractor began construction on the project, it was necessary for the telecommunication providers, Optimum and Frontier, to relocate their overhead utilities underground along the corridor. However, after construction began, it was discovered that the relocated utilities were not in the correct location and conflicted with a proposed storm sewer that could not be adjusted. To address this, both utilities were asked to relocate once more. We appreciate their efforts in helping us resolve this matter.
  • To maintain progress while the main construction was halted, the city's contractor continued work on secondary items such as installing new underground utilities along South College Avenue.
  • Although the city's contractor was able to proceed with some construction activities, the delay in storm sewer installation significantly impacted the project timeline and became the critical path. The total estimated delay in the project due to telecom relocations is eight months.

Redesign to Remove Medians

  • After receiving public feedback on other median projects in the area, the City Council began workshop discussions in late 2023 to consider removing medians from the South College Avenue project. In February 2024, after coordinating with the design engineer, Engineering Services presented design options for removing the medians, and the City Council provided official direction to remove the medians from the project. The redesign of the roadway cross-section required a temporary halt in construction while the design consultant modified the roadway plans and a change order was issued to adjust construction quantities. The total estimated delay in the project due to the median redesign is four months.

We appreciate your patience throughout this process. Despite these challenges, we remain committed to delivering safer vehicular and pedestrian routes, improved accessibility to Midtown Park and Downtown Bryan, and enhanced aesthetics along this important and culturally significant corridor. Your understanding and cooperation are invaluable as we work towards these improvements.


Project Timeline and Estimated Completion Schedule

Below is a timeline of events and an estimated completion schedule. Please note that the forecasted dates are based on coordination with the City's contractor, Larry Young Paving. Actual completion dates may occur earlier or later, depending on the contractor's progress.

February - March, 2023 - Project Bid

The South College Avenue Reconstruction Phase 1 project is bid for construction. Bids are evaluated and Larry Young Paving, LLC (LYP) is preliminarily selected as the contractor.

March 28, 2023 - City Council Approves Construction Contract

LYP is officially choses as the contractor and the City enters a construction contract with LYP.

May, 2023 - Construction Starts

Property owners are notified of the start of construction work for the South College Avenue Reconstruction project.

August, 2023 - Telecoms Issue Identified

Newly installed underground telecommunication lines are found to be in conflict with the proposed storm sewer lines. The storm sewer lines proposed with the South College project cannot be relocated and conversations with telecom companies to relocate their lines are started. While relocations are happening, LYP and their subcontractors continue to install water and sewer lines.

August 22, 2023 - City Council Workshop on Median Removal

Due to comments received by homeowners, businesses, and citizens affected by recent projects wherein medians were installed, the City Council discusses options to remove medians from the project.

September 5, 2023 - 2nd City Council Workshop on Median Removal

Discussion continues on options to remove medians from the project. City Council requests the engineering department to seek additional roadway cross sections from the design engineer for comparison.

December, 2023 - Creek Crossing is completed

LYP finishes construction of the box culvert crossing of the creek near Villa Maria.

February, 2024 - All Telecoms are Relocated

All telecoms are relocated out of the way of the proposed storm sewer.

February 23, 2024 - Medians Removed

During the 3rd City Council Workshop on Median Removal, revised roadway cross sections are presented to the City Council and the current (revised) roadway cross section is selected. The Engineering Department seeks a design cost and proposal from the design engineer to revise the construction plans to reflect the newly selected design.

March 2024 - Engineering Redesign is Completed

The design engineer competes the redesign and provides a new construction plan set and construction quantities. The Engineering Department uses this information to coordinate a construction contract change order.

April 16, 2024 - Monthly Update Letter Starts

An project status update letter is sent to residents, land owners, and business owners within the project boundary. From April onwards, monthly update letters are sent out and posted to the CIP page.

April 25, 2024 - Construction Contract Change Order is Approved

The construction contract change order that reflects the revised plans and unit quantities is executed. The contractor is given the greenlight to resume construction on the roadway.

May, 2024 - Construction Resumes

LYP resumes significant construction activities including grading, subgrade stabilization, and storm sewer installation.

August 22, 2024 - Concrete Pouring Resumes

LYP hand pours approximately 200 LF of roadway from Villa Maria Road to past the box culverts crossing.

August 30, 2024 - Slipform Paving of the Northbound lane

LYP uses a slipform paver to pour approximately 1,700 LF of roadway from Dellwood St. to Bizzell St.

November 4, 2024 - Villa Maria to Dellwood Section Opened

Opening from Villa Maria Road to Dellwood Street.

November 15, 2024 - Dellwood to Edge Street Opened

Opening from Dellwood Street to approximately 100 feet north of Edge Street.

November 22, 2024 - Roundtree Drive Intersection Opened

Opening from 100 feet north of Edge Street to 100 feet south of Bizzell Street, including the Rountree Drive intersection.

December 20, 2024 - Bizzell Street Intersection Opened

Opening from 100 feet south of Bizzell Street to 150 feet north of Bizzell Street was completed and opened.

Est. Summer 2025 - Construction Completion

Estimated Final Completion of the South College Avenue Phase 1 project.

Construction Photos

Completed Section of Roadway from Villa Maria Roadway to Dellwood Street.

Northbound Lane Roadway - Aerial photos showing the first section of new concrete roadway

Slipform Paving - Machinery used to pave South College Avenue

Subgrade Preparation - Lime stabilization of the subgrade

Aerials of South College Avenue - pre-stabilization

Subgrade Preparation - Photos obtained during the grading process

Construction of the box culvert crossing under South College Avenue near Villa Maria Road


Roadway Design - South College Ave "Reconstruction"

Comparison of Roadway Cross Sections

Comparison of typical South College Avenue roadway sections: On the left is the original reconstruction project cross section, which includes medians, and on the right is the revised cross section, where the medians have been removed.


Revised Intersections and Pedestrian Crossings

Villa Maria Rd Intersection

Villa Maria Rd Intersection. Click to expand.

The Villa Maria Road intersection will maintain pre-project traffic patterns. A median will be installed at this intersection to protect southbound traffic. A sidewalk will be installed on the northern side of the roadway.

Dellwood Street Intersection

Dellwood Street Intersection. Click to expand.

There will be minimal changes to the existing Dellwood Street intersection. Vehicles turning onto South College Avenue will encounter a stop sign, while South College Avenue will maintain the right of way and not have a stop sign. Additionally, a pedestrian sidewalk will run parallel to South College Ave and cross Dellwood Street.

Davis Street Intersection

Davis Street Intersection. Click to expand.

There will be minimal changes to the existing Davis Street intersection. Vehicles approaching South College Avenue from Davis Street will encounter a stop sign, while traffic on South College Avenue will not have a stop sign and will maintain right of way. Additionally, a pedestrian sidewalk will run parallel to South College Avenue and cross Davis Street.

Edge Street Intersection

Edge Street Intersection. Click to expand.

There will be minimal changes to the existing Edge Street intersection. Vehicles approaching South College Avenue from Edge Street will encounter a stop sign, while traffic on South College Avenue will not have a stop sign and will maintain right of way. Additionally, a pedestrian sidewalk will run parallel to South College Ave and cross Edge Street.

Rountree Drive Intersection

Rountree Drive Intersection. Click to expand.

The new design of the Rountree Drive Intersection features a dedicated crosswalk that will connect the shared use path on either side of Rountree Drive. Vehicles approaching South College Avenue from Rountree will be required to stop behind the crosswalk, as marked by the stop sign and stop bar. Traffic on South College Avenue will not have a stop sign and maintain right of way.

Bizzell St Intersection

Bizzell St Intersection. Click to expand.

There will be minimal changes to the existing Bizzell Street intersection. Vehicles approaching South College Avenue from Bizzell Street will encounter a stop sign, while traffic on South College Avenue will not have a stop sign and will maintain right of way. Additionally, a pedestrian sidewalk will run parallel to South College Ave and cross Edge Street.

Koening St Intersection

Koening St Intersection. Click to expand.

There will be minimal changes to the existing Koening Street intersection. Vehicles approaching South College Avenue from Koening Street will encounter a stop sign, while traffic on South College Avenue will not have a stop sign and will maintain right of way. Additionally, a pedestrian sidewalk will run parallel to South College Ave and cross Koening Street.

Pedestrian Refuge No. 3

Pedestrian Refuge No. 3. Click to expand.

The existing crosswalk that crosses South College Avenue at Waverly Drive will be upgraded to a pedestrian refuge. This style of crossing provides a much safer crossing to citizens crossing from the pedestrian sidewalk to the shared use path. Traffic on South College Avenue will be required to yield to pedestrians.

Waverly Drive Intersection

Waverly Drive Intersection. Click to expand.

Vehicles approaching South College Avenue from Waverly Drive will encounter a stop sign, while traffic on South College Avenue will not have a stop sign and will maintain right of way. Vehicles turning left on to South College Avenue from Waverly Drive will see a smaller turning radius. Vehicles should pull further into the intersection before turning the steering wheel. Additionally, a pedestrian sidewalk will run parallel to South College Ave and cross Waverly Drive.

Highland Drive Intersection

Highland Drive Intersection. Click to expand.

There will be minimal changes to the existing Highland Drive intersection. Vehicles approaching South College Avenue from Highland Drive will encounter a stop sign, while traffic on South College Avenue will not have a stop sign and will maintain right of way. Additionally, a pedestrian sidewalk will run parallel to South College Ave and cross Highland Drive.

Hollydale Street and Williamsons Drive Roundabout

Hollydale Street and Williamsons Drive Roundabout. Click to expand.

The two previously separate intersections of Hollydale Street and Williamsons Drive will be consolidated into a single roundabout. Traffic entering the roundabout will be required to yield to vehicles already circulating within the roundabout. Additionally, vehicles approaching the roundabout must yield to pedestrians crossing at the crosswalks surrounding the roundabout. Drivers should reduce their speed as they approach the roundabout to ensure safe entry and navigation. This speed reduction allows them to yield to both vehicles already in the roundabout and pedestrians using the crosswalks.

Pedestrian Refuge No. 2

Pedestrian Refuge No. 2. Click to expand.

Another pedestrian refuge is provided for crossing to citizens cross from the pedestrian sidewalk to the shared use path near the Hollydale Street Roundabout. Traffic on South College Avenue will be required to yield to pedestrians.

Lake Street Intersection

Lake Street Intersection. Click to expand.

There will be minimal changes to the existing Lake Street intersection. Vehicles approaching South College Avenue from Lake Street will encounter a stop sign, while traffic on South College Avenue will not have a stop sign and will maintain right of way. Additionally, a pedestrian sidewalk will run parallel to South College Ave and cross Lake Street.

Pedestrian Refuge No. 1

Pedestrian Refuge No. 1. Click to expand.

Another pedestrian refuge is provided for crossing to citizens cross from the pedestrian sidewalk to the shared use path between Howard Street and Lake Street. Traffic on South College Avenue will be required to yield to pedestrians.

Howard Street Intersection

Howard Street Intersection. Click to expand.

There will be minimal changes to the existing Howard Street intersection. Vehicles approaching South College Avenue from Howard Street will encounter a stop sign, while traffic on South College Avenue will not have a stop sign and will maintain right of way. Additionally, a pedestrian sidewalk will run parallel to South College Ave and cross Howard Street.

Carson Street Roundabout

Carson Street Roundabout. Click to expand.

The Carson Street Intersection will be completely redesigned to promote traffic flow. Traffic entering the roundabout will be required to yield to vehicles already circulating within the roundabout. Additionally, vehicles approaching the roundabout must yield to pedestrians crossing at the crosswalks surrounding the roundabout. Drivers should reduce their speed as they approach the roundabout to ensure safe entry and navigation. This speed reduction allows them to yield to both vehicles already in the roundabout and pedestrians using the crosswalks.

Villa Maria Rd Intersection

The Villa Maria Road intersection will maintain pre-project traffic patterns. A median will be installed at this intersection to protect southbound traffic. A sidewalk will be installed on the northern side of the roadway.

Dellwood Street Intersection

There will be minimal changes to the existing Dellwood Street intersection. Vehicles turning onto South College Avenue will encounter a stop sign, while South College Avenue will maintain the right of way and not have a stop sign. Additionally, a pedestrian sidewalk will run parallel to South College Ave and cross Dellwood Street.

Davis Street Intersection

There will be minimal changes to the existing Davis Street intersection. Vehicles approaching South College Avenue from Davis Street will encounter a stop sign, while traffic on South College Avenue will not have a stop sign and will maintain right of way. Additionally, a pedestrian sidewalk will run parallel to South College Avenue and cross Davis Street.

Edge Street Intersection

There will be minimal changes to the existing Edge Street intersection. Vehicles approaching South College Avenue from Edge Street will encounter a stop sign, while traffic on South College Avenue will not have a stop sign and will maintain right of way. Additionally, a pedestrian sidewalk will run parallel to South College Ave and cross Edge Street.

Rountree Drive Intersection

The new design of the Rountree Drive Intersection features a dedicated crosswalk that will connect the shared use path on either side of Rountree Drive. Vehicles approaching South College Avenue from Rountree will be required to stop behind the crosswalk, as marked by the stop sign and stop bar. Traffic on South College Avenue will not have a stop sign and maintain right of way.

Bizzell St Intersection

There will be minimal changes to the existing Bizzell Street intersection. Vehicles approaching South College Avenue from Bizzell Street will encounter a stop sign, while traffic on South College Avenue will not have a stop sign and will maintain right of way. Additionally, a pedestrian sidewalk will run parallel to South College Ave and cross Edge Street.

Koening St Intersection

There will be minimal changes to the existing Koening Street intersection. Vehicles approaching South College Avenue from Koening Street will encounter a stop sign, while traffic on South College Avenue will not have a stop sign and will maintain right of way. Additionally, a pedestrian sidewalk will run parallel to South College Ave and cross Koening Street.

Pedestrian Refuge No. 3

The existing crosswalk that crosses South College Avenue at Waverly Drive will be upgraded to a pedestrian refuge. This style of crossing provides a much safer crossing to citizens crossing from the pedestrian sidewalk to the shared use path. Traffic on South College Avenue will be required to yield to pedestrians.

Waverly Drive Intersection

Vehicles approaching South College Avenue from Waverly Drive will encounter a stop sign, while traffic on South College Avenue will not have a stop sign and will maintain right of way. Vehicles turning left on to South College Avenue from Waverly Drive will see a smaller turning radius. Vehicles should pull further into the intersection before turning the steering wheel. Additionally, a pedestrian sidewalk will run parallel to South College Ave and cross Waverly Drive.

Highland Drive Intersection

There will be minimal changes to the existing Highland Drive intersection. Vehicles approaching South College Avenue from Highland Drive will encounter a stop sign, while traffic on South College Avenue will not have a stop sign and will maintain right of way. Additionally, a pedestrian sidewalk will run parallel to South College Ave and cross Highland Drive.

Hollydale Street and Williamsons Drive Roundabout

The two previously separate intersections of Hollydale Street and Williamsons Drive will be consolidated into a single roundabout. Traffic entering the roundabout will be required to yield to vehicles already circulating within the roundabout. Additionally, vehicles approaching the roundabout must yield to pedestrians crossing at the crosswalks surrounding the roundabout. Drivers should reduce their speed as they approach the roundabout to ensure safe entry and navigation. This speed reduction allows them to yield to both vehicles already in the roundabout and pedestrians using the crosswalks.

Pedestrian Refuge No. 2

Another pedestrian refuge is provided for crossing to citizens cross from the pedestrian sidewalk to the shared use path near the Hollydale Street Roundabout. Traffic on South College Avenue will be required to yield to pedestrians.

Lake Street Intersection

There will be minimal changes to the existing Lake Street intersection. Vehicles approaching South College Avenue from Lake Street will encounter a stop sign, while traffic on South College Avenue will not have a stop sign and will maintain right of way. Additionally, a pedestrian sidewalk will run parallel to South College Ave and cross Lake Street.

Pedestrian Refuge No. 1

Another pedestrian refuge is provided for crossing to citizens cross from the pedestrian sidewalk to the shared use path between Howard Street and Lake Street. Traffic on South College Avenue will be required to yield to pedestrians.

Howard Street Intersection

There will be minimal changes to the existing Howard Street intersection. Vehicles approaching South College Avenue from Howard Street will encounter a stop sign, while traffic on South College Avenue will not have a stop sign and will maintain right of way. Additionally, a pedestrian sidewalk will run parallel to South College Ave and cross Howard Street.

Carson Street Roundabout

The Carson Street Intersection will be completely redesigned to promote traffic flow. Traffic entering the roundabout will be required to yield to vehicles already circulating within the roundabout. Additionally, vehicles approaching the roundabout must yield to pedestrians crossing at the crosswalks surrounding the roundabout. Drivers should reduce their speed as they approach the roundabout to ensure safe entry and navigation. This speed reduction allows them to yield to both vehicles already in the roundabout and pedestrians using the crosswalks.


Public Impacts

Roadway Closures

Expect to see disruption to traffic during construction including daily and overnight lane closures. Please note that when there are complete street closures, access for residents is required to be provided by our contractor - Larry Young Paving. Additionally, You will be notified by the general contractor to coordinate access to your home, as needed.

Lime Stabilization

This project will be utilizing lime stabilization of the subgrade. Lime stabilization involves mixing lime into the soil to improve its strength and stability. During this process, lime dust can become airborne, which may be noticeable to residents nearby. The City of Bryan Engineering Department has instructed the contractor to spray down the lime to minimize the dust and reduce any potential nuisance.

Early Work / Weekend Work

To minimize disruption of business traffic and resident access to their homes, the city has authorized LYP to perform construction activities outside of normal construction hours (7 a.m. to 7 p.m., Monday through Saturday).  For any work outside these hours, the contractor is required to provide at least 48 hour notice to affected businesses and residents via a door hanger.

Utility Outages

Utility outages including temporary water shut-offs may be required to connect private service lines into the newly installed water and sewer mains. You will be notified of any utility outages and any early-work by the contractor at least 48 hours beforehand.

Feedback and Comments?

If you've would like to provide comments on the project, please click the link below or visit  https://weblink.bryantx.gov/Forms/south-college-phase1  and complete feedback form.


Project Maps

Area Map

Use the arrows on the sides to navigate maps.

Sewer Upgrades

Use the arrows on the sides to navigate maps.

Phasing Map

Use the arrows on the sides to navigate maps.

South College Avenue Reconstruction Project Aerial Facing East

 Links and Resources 

Access essential resources and tools for the City of Bryan Engineering through the following links. Simply click on the button and you will be redirected to our most frequently used services and documents.

To stay informed between these monthly updates, please click the "Social Media Sites" button below and follow the City on your preferred platform.

Comparison of typical South College Avenue roadway sections: On the left is the original reconstruction project cross section, which includes medians, and on the right is the revised cross section, where the medians have been removed.

Renderings of Hollydale Street and Williamson Drive Roundabout from Original Concept

Renderings of Carson Street Roundabout from Original Concept

Please note that the task categories listed under "Item Description" may include subtasks that are indirectly related but essential for overall completion. For example, waterline items include the demolition and repair of concrete pavement as necessary for the installation of the waterline.