Welcome to the Warm Springs Avenue, Avenue C to Windsong Drive Concept Study Online Meeting.
Thank you for your interest in this important study.
Please scroll down to view the information.
ACHD is engaging the public as part of the study to identify and recommend pedestrian and bike facility improvements along Warm Springs Avenue from Avenue C to Windsong Drive.
Recognizing the unique character of different sections of Warm Springs Avenue, the study area is divided into three segments.
- Avenue C to Coston Street
- Coston Street to Old Penitentiary Road
- Old Penitentiary Road to Windsong Drive
Public Workshop
ACHD is hosting a public workshop on June 22, 2023, at Adams Elementary School Gym, 1725 Warm Springs Avenue, to share the results of the survey conducted earlier this spring. The facilitated workshop will be an opportunity to help ACHD identify areas of concern within the project area and brainstorm potential solutions. Please plan on attending one of two sessions:
- Session 1: 2:30 p.m. – 4 p.m.
- Session 2: 5 p.m. – 6:30 p.m.
Parking is available in the highlighted sections on the map. A few spots are also available on Warm Springs Avenue, outside of the bus-only area. We encourage those who live close to Adams Elementary to walk or bike to the school, if possible.
If you have specific concerns about possible impacts to your property, please email projects@achdidaho.org or call Edinson Bautista at 208-387-6100 ahead of the public meeting/workshops on June 22, 2023.
Crash History
- Along the study corridor a total of 95 crashes were reported between 2017 and 2021, with the largest portion being rear-end crashes, making up 43% of the total.
- Hitting a fixed object and angle/angle turning crashes accounted for 18% and 15% of all crashes.
- 42 of the crashes resulted in injuries to one or more persons involved in the crash.
- The other 53 crashes were property damage only (PDO).
- There were no fatal crashes reported.
- A total of five bike and two pedestrian crashes occurred, accounting for 7% of the recorded crashes within the study area.
- Six of the seven pedestrian/bike crashes occurred between Avenue C and Coston Street.
Maps depicting each crash within the corridor are shown below.
Warm Springs Avenue, Avenue C to Coston Street
Warm Springs Avenue, Coston Street to Old Penitentiary Road
Warm Springs Avenue, Old Penitentiary Road to Windsong Drive
Traffic Count Data
Current traffic volumes along Warm Springs Avenue and roadways within the study area are as follows:
Survey Responses
ACHD conducted an online survey April 19 through May 3, 2023 to ask residents, business owners, and anyone who uses Warm Springs Avenue to answer a series of questions to learn about how people use Warm Springs and the issues they are experiencing.
617 people responded to the survey. Here’s what we learned:
When asked what description best fit, participants answered in the following ways:
What type of transportation do you typically use on Warm Springs?
Do you think Warm Springs needs improvements?
If yes, for what type of transportation? Please select as many answers as apply.
What improvements should be considered for Warm Springs between Avenue C and Old Penitentiary Road and for between Old Penitentiary Road and Windsong Drive?
The top two themes were the same for both sections.
What ideas for enhancing Warm Springs for all users will best “fit” the area?
Thinking along the same line, what ideas don’t “fit” the neighborhood?
What existing features or conditions on Warm Springs should be preserved or enhanced, if possible?
What should our priorities be as we work to improve Warm Springs?
What else should ACHD be thinking about when considering ways to improve Warm Springs?
Did we miss anything?
ACHD Warm Springs Ave Study Concerns
Schedule/Next Steps
June 22
Public Outreach Meeting / Workshops
Fall 2023
Second Public Outreach Meeting
Spring 2024
Third Public Outreach Meeting
Summer 2024
Commission Hearing / Adoption
Comment Form
Warm Springs Comment Form
For questions or more information, contact:
Edinson Bautista, ACHD Senior Transportation Planner
208.387.6100 or TTY: 1-800-377-3529 projects@achdidaho.org
To arrange for a translator or other accommodation, contact ACHD at (208) 387-6100 | TTY: 1-800-377-3529 | projects@achdidaho.org