TC Energy Mill Creek Oil Spill Emergency Response

Oil Pollution Act (OPA) emergency response activities and information tracking.


Response Overview

On December 7, 2022, a TC Energy pipeline, part of the Keystone pipeline system, ruptured south of where it crosses Mill Creek northeast of Washington, Kansas. An estimated 588,000 gallons were discharged. The Washington County, Kansas Emergency Management Agency constructed a large underflow dam to provide containment and prevention of oil from migrating downstream. EPA On-Scene Coordinators responded and remained at the site to direct oil response and removal activities.

Images depicting initial site conditions including oil entering Mill Creek, oiled vegetation, and initial pipeline repair and cleanup activities.


Response Activities

In early October 2023, restoration work within Mill Creek was completed. The restoration work was conducted under Nationwide Permit 27 authorized by the U.S. Army Corps of Engineers (USACE). On October 12, 2023, all dams and diversions were removed and natural flow of Mill Creek resumed. EPA has completed a final visual inspection of Mill Creek while under natural flow conditions and no areas of concern were noted.  No additional oil removal activities within Mill Creek are planned. Restoration activities remain ongoing at the site, but are focused on upland restoration. Additionally, the restoration of the response footprint is ongoing to ensure the impacted area is returned to pre-incident conditions. The water treatment system and associated ponds have been decommissioned in accordance with applicable requirements and backfilled to grade. With oil removal activities complete, EPA has transitioned Response Command to Kansas Department of Health and Environment (KDHE) and TC Energy.

Images depicting response activities including water treatment and stream cleanup activities.

Operational Areas Tracking

For oil removal tracking, the approximate 3.5 mile segment of Mill Creek impacted by the oil spill was divided in to 100-foot sections, called Operational Areas (OA). In total, there are 216 OAs. Following removal of all oil-impacted water, debris, sediment, and vegetation; each OA was thoroughly inspected for any remaining oil that may act as a persistent source of pollution to Mill Creek. As of May 11, 2023, all of the OAs passed EPA inspection and oil removal work was considered complete. The map and dashboard below provide cleanup progress metrics for OA inspections and Mill Creek surface water treated. The map shows that oil removal is complete at all 216 OAs.


Response Timeline

October 13, 2023

EPA completes a final visual inspection of the impacted portion of Mill Creek. On October 12, 2023, all dams and diversions were removed from the creek, returning flow to natural conditions.  No oil, sheening, or areas of concern were identified during the inspection. With oil removal activities complete, EPA transitioned Response Command to KDHE and TC Energy.

Picture depicting final stream restoration.

June 1, 2023

Following completion of oil removal activities within the 216 OAs in Mill Creek, the impacted stretch of the creek was refilled with water to levels above normal flow conditions to ensure oil-impacted creek banks were saturated. Water was maintained at this level for 5 days and visual inspections were conducted. This activity was completed to identify any residual areas of oil or oil-contaminated soil/sediment that require further cleanup. No sheening or oil associated with a source that could be addressed was observed in these segments. The full extent of Mill Creek, impacted by the oil spill, has been visually inspected and no areas of concern have been noted.

Picture depicting creek refilling to ensure bank saturation and stabilization.

May 11, 2023

Approximately 3.5 miles of Mill Creek have been dewatered and oil removal activities completed for all 216 OAs within the oil-impacted segment of Mill Creek. Response activities ongoing include completion of excavation work at the pipeline discharge location to remove the remaining oil-contaminated soil, disposal of oil-impacted soil and sediment, and the restoration of lands impacted by the response. All wastes generated during the cleanup are being sampled for characterization and transported for disposal at appropriate off-site facilities. Phase II Diversion of Mill Creek remains in operation to allow for restoration activities to be conducted.

May 8, 2023

On May 8, 2023, the USACE authorized TC Energy to begin restoration work on Mill Creek under Nationwide Permit 27.

March 11, 2023

Approximately 2.2 miles of Mill Creek remain dewatered. Phase II Diversion of Mill Creek is completed and begins operation. Construction and implementation of the surface water treatment system completed. Daily effluent of treated surface water confirmed no detectable concentration of oil-related contaminants.

March 2, 2023

Approximately 2.2 miles of Mill Creek has been dewatered to allow for in-channel oil-impacted bank and sediment removal. Mill Creek has been anecdotally divided in to 100-foot sections, called Operational Areas. Following removal of all oil-impacted water, sediments, and vegetation; each Operational Area will be qualitatively and quantitatively assessed to determine if cleanup standards have been accomplished. Construction of improved diversion and surface water treatment system is on-going.

February 16, 2023

Approximately 1.25 miles of Mill Creek has been dewatered to allow for in-channel oil-impacted bank and sediment removal. Construction of a Phase II diversion system begins, which will increase the volume of surface water that can be diverted from 20 cubic feet per second (cfs) to 100 cfs. Construction of the surface water treatment system continues. Two members of the U.S. Coast Guard - Atlantic Strike Team mobilize to the response to support EPA oversight activities.

February 9, 2023

TC Energy begins construction of a large surface water treatment system, including a 5-acre treatment pond with a volume of 18.8 million gallons, and begins dewatering Mill Creek. Removing surface water from the creek will allow TC Energy to efficiently recover oil impacted banks and sediments through manual and mechanical tactics.

January 26, 2023

Sample results from domestic-use drinking water wells do not identify any contamination associated with the discharged oil. Freezing conditions again complicate oil removal progress.

January 25, 2023

TC Energy completes bulk oil recovery. To illustrate oil recovery progress, the extent of oil that was bank-to-bank on Mill Creek on December 15, 2022, was approximately 1.5 miles in length. Additionally, oil on the surface of Mill Creek measured more than 10 inches in depth in portions of that 1.5 mile stretch. As of January 25, 2023, the extent of bank-to-bank oil was approximately 500 feet in length and the depth of oil on the creek surface was generally less than 1 inch. Recovery tactics begin shifting to address the remaining areas of oil on the surface water, banks, and sediments of Mill Creek.

January 19, 2023

Improved weather conditions and implementation of effective recovery tactics have reduced the heaviest oiling of Mill Creek to locations in and around the 20th Road bridge.

January 17, 2023

Agencies including the U.S. Army Corp of Engineers, U.S. Fish and Wildlife Service, and Kansas State Historic Preservation Office are consulted on TC Energy's requirements during the response to remove oil from Mill Creek.

January 14, 2023

KDHE rescinds the Mill Creek stream advisory downstream of 21st Street bridge due to improved surface water conditions that were a result of the diversion implementation.

January 6, 2023

EPA issues TC Oil Pipeline Operations, Inc. a Clean Water Act Section 311 (c) and (e) enforcement order to ensure a comprehensive approach to assessment and cleanup activities under EPA's oversight.

January 5, 2023

TC Energy completed isolation of the impacted reach of Mill Creek and implemented a diversion that pumps surface water upstream of the pipeline rupture to a location downstream of the underflow dams. The National Weather Services begins provided support to response.

December 29, 2022

TC Energy completes repair and restarts the Keystone pipeline.

December 26, 2022

TC Energy begins using mechanical recovery operations to collect ice and oil due to freezing conditions. Recovery locations are limited to areas in and around the 20th Road bridge.

December 22, 2022

KDHE issues TC Energy an emergency order for effluent standards for treated water discharge.

December 18, 2022

Freezing conditions begin to slow oil recovery operations.

December 13, 2022

EPA deployed an additional three OSCs for response oversight. A second underflow dam was constructed downstream of the first underflow dam. An estimated 3.74 miles of Mill Creek were visibly impacted, of which 1.32 miles remained heavily impacted. Oil recovery tactics include the use of vacuum trucks and skimmers. Other primary response activities include:

  • Air monitoring
  • Pipeline repair
  • Oil impacted soil excavation
  • Surface water sampling
  • Wildlife assessments

December 10, 2022

EPA deployed an additional OSC and two START contractors and established roving air monitoring points at perimeter locations near residential properties.

Perimeter Air Monitoring Locations

December 9, 2022

Kansas Department of Health and Environmental issues a Stream Advisory for Mill Creek from 18th Road to it's confluence with the Little Blue River.

KDHE Logo.

December 8, 2022

TC Energy made notification to the National Response Center, who contacted Region 7 EPA. EPA responded with two On-Scene Coordinators (OSC). Upon arrival, a Unified Command was established. Oil recovery response operations began 24-hour operational periods.

TC Energy Mill Creek Oil Spill StoryMap

U.S. EPA Region 7

Photos by

EPA