Mt. Charleston Recovery Meeting

October 11, 2023

Area 1 - Mary Jane Falls Trailhead

Debris at trailhead sign and restroom

Forestry service states the trail and trailhead are inoperable without cleanup efforts

Rock debris deposited in flow path. 2019 OA MPU shows contributing watersheds converge at bottom of canyon with 100-year flow rate of 5638 cfs.

Tree debris swept in the flow path

Looking downstream from trail area (southwest of trailhead)

Debris and tree-fall causing damage to the restroom roof

Rip-rap along SNWA well site (repair needed)

Channel flow path downstream of trailhead parking area

Area 2 - Echo Road

K-Rails put along roadway to maintain flow path on forest side. Berm washed out leading to destruction of paved road and impacting residents on north side of Echo Rd

Material put back along Echo Rd, but recommend compaction and engineered solution to avoid washout in future rain events

CCPW has 30-ft ROW and only 20-ft pavement. Majority, if not all, of existing berm on forestry land. Recommend berm integrity to maintain flow path on intended forest side and not on Echo Rd

Spring flows from the north conveyed through headwall and culvert under Echo Rd to get it back to southern forest side to protect Echo Rd

Standing on forest side, adjacent to Echo Rd, significant erosion along flow path. Dirt material placed back along Echo Rd but would need long term solution to protect roadway and housing along Echo Rd

Another look at erosion along flow path

Erosion on housing side along Echo Rd (note this is post cleanup of significant debris on Echo Rd)

No separation from Echo Rd and forest flow path near housing, recommend berm to direct and maintain flows on forest side to protect life and property along Echo Rd.

Area 3 - NDOT Bridge

NDOT completed post rain event grouted rip-rap along bridge abutments and added new armoring along Echo Rd side (due to flows on Echo Rd from berm failure)

Looking upstream from NDOT Bridge, note new grouted rip-rap armoring on side slopes

NDOT mentioned no engineering plans in emergency fix: just eye-ball and match grading. Maybe be able to excavate further if grading allows to get more capacity

NDOT Bridge B-609, some damage to abutment was repaired

Area 4 - Mt. Charleston Library

Newly graded channel upstream of the culvert at the CC Library. Small loose rip-rap likely to be washed out in larger rain events and clog CC library culvert

Looking downstream to culvert at CC Library, unlikely to have capacity for 100-year event from the 2019 OA MPU. Loose rip-rap likely to cause clogging issues in future rain events. Note: Post rain event had debris above railing

Downstream of culvert at CC Library. Significant erosion. Note: During the rain event, flow path bisected the CC Library and swept through Old Town through this channel and on Aspen Rd

Another look upstream from the culvert at the CC library

Area 5 - Old Town and Lundy ES

Flow path bisected the CC Library and swept through Old Town.

Finished grade on Aspen Road washed out approximately 3-ft from rain event

Another look at washed out Aspen Rd

Flow path in channel behind Mahogany Drive at the back of houses

Close-up of channel behind houses on Mahogany Drive

Culvert in Old Town with significant debris. Clogging and lack of capacity during rain event caused erosion as flows swept through Old Town

Looking downstream at the Old Town culvert

Pedestrian bridge (connection washed out) just before Lundy ES

Pedestrian bridge culvert, storm flow path was to the south and washed out the path into the forest

Looking upstream from the pedestrian bridge

Looking upstream at washed out area beyond the pedestrian bridge culvert

Lundy ES, significant amount of material and large rock was brought back to fill in the erosion

30 trucks of concrete was brought in and pumped into the ground to stabilize Lundy ES

Lundy ES post event and post recovery comparison. Significant material brought back to fill in erosion

Area 6 - Existing MPU Crossing

Rainbow Canyon RCB washed out by rain event

Looking towards street sign from washed out 8'x4' RCB. MPU shows 7441 cfs in 100-year and to be replaced with ultimate facility of 105'W x 4.5'D bridge crossing

Looking downstream from washed out RCB

Close-up of washed out RCB. Recommend replace in-kind when CCPW is ready with MWP funding from CCRFCD,

Another view downstream from washed out RCB

Tire at washed out RCB location

Robust tree at washed out RCB location

CCW

RFCD