Revitalize Rose Avenue
A Pedestrian Connectivity and Beautification Project
Project Overview


(Left) Existing un-improved City sidewalk on rose ave. (Right) Existing Frederick Park.
Revitalize Rose Avenue: A Pedestrian Connectivity and Beautification Project spans from Frederick Street to Glenavon Avenue on the northside of Rose Avenue. In addition this project will create pedestrian connections to the existing Frederick Street Park. The overall project consists of the following elements:
- 14,000 sf. of aggregate sidewalk
- 10,000 sf. of new water-wise landscaped area
- 6 New ADA access ramps
- Crosswalks at Courtland Street and Penmar Avenue
- Lighting enhancements at crosswalks
- Existing driving and bicycle lanes will remain in place
- Tree protection bumpout
Revitalize Rose Avenue will be generously funded by the Office of Councilwoman Traci Park, Council District 11. This project will be designed and implemented by the Bureau of Street Services (StreetsLA).
Project Location
Overall Project Limit of Work
Before and After Renderings
Proposed Tree Protection Bumpout
Proposed Meandering Sidewalk and Landscape Planting
Timeline & Next Steps
2024
August 10, 2024 In-Person community outreach event
August 12, 2024 Virtual community outreach event
August 26th, 2024 Rec & Park's replacing golf course fence
2025
WINTER 2024/2025 Design completion
SPRING/SUMMER 2025 Start of construction
FALL/WINTER 2025 Project Completion