Revitalize Rose Avenue

A Pedestrian Connectivity and Beautification Project

Project Overview

(Left) Existing un-improved City sidewalk on rose ave. (Right) Existing Frederick Park.

Revitalize Rose Avenue: A Pedestrian Connectivity and Beautification Project spans from Frederick Street to Glenavon Avenue on the northside of Rose Avenue. In addition this project will create pedestrian connections to the existing Frederick Street Park. The overall project consists of the following elements:

  • 14,000 sf. of aggregate sidewalk
  • 10,000 sf. of new water-wise landscaped area
  • 6 New ADA access ramps
  • Crosswalks at Courtland Street and Penmar Avenue
  • Lighting enhancements at crosswalks
  • Existing driving and bicycle lanes will remain in place
  • Tree protection bumpout

Revitalize Rose Avenue will be generously funded by the Office of Councilwoman Traci Park, Council District 11. This project will be designed and implemented by the Bureau of Street Services (StreetsLA).

Project Location

Overall Project Limit of Work

Before and After Renderings

Proposed Tree Protection Bumpout

Proposed Meandering Sidewalk and Landscape Planting

Timeline & Next Steps

2024

August 10, 2024   In-Person community outreach event  

August 12, 2024   Virtual community outreach event 

August 26th, 2024  Rec & Park's replacing golf course fence 

2025

WINTER 2024/2025  Design completion 

SPRING/SUMMER 2025  Start of construction 

FALL/WINTER 2025  Project Completion 

Connect with Us!

Email: streetsla.ert@lacity.org Phone: 213.913.2117

Overall Project Limit of Work

Proposed Tree Protection Bumpout