
Beaver Creek Dam
Chester County, Pennsylvania
History
Originally constructed in 1976 as part of the Brandywine Watershed Plan, the Beaver Creek Dam provides flood reduction for communities that border the Beaver Creek, East Branch Brandywine Creek and the main tributary of the Brandywine Creek. NRCS is providing technical support and financial assistance to Chester County Water Resources Authority (CCWRA) to extend the life of the dam and rehabilitate the dam to meet state and federal safety standards. Once work is completed, the Beaver Creek Flood Control Dam will continue to provide flood control functions, enhance wildlife habitat and improve water quality in Beaver Creek.
Timeline (courtesy CCWRA)
July 2021
Construction activities for the week of July 26 include continued excavation in the auxiliary spillway including dewatering of collected water. Activities planned for the week of August 2nd include continued excavation as well as rock surface preparation, and placing initial backfill concrete.
August 2021
Continued excavation, cleaning rock surface, and establishing concrete plant next to spillway. Test pad for placing roller compacted concrete, dewatering, and placing initial backfill.
September 2021
Initial work on toe drain clean outs
October 2021
Placing concrete in spillway backfill crop structure in auxiliary spillway and install cofferdam around riser.
November 2021
Roller-compacted concrete drop structure completed. Auxiliary spillway is rough graded, top soil spread, and winter rye planted.
December 2021
Riser construction begun.
January 2022
Construction of the auziliary spillway is complete with seed, mulch and matting installed.
Feb to July 2022
Eagle nesting season - construction halted
August 2022
Riser construction completed: reinforced steel and formwork for the riser lid and hatch, cement poured and finished
September 2022
Forms removed from riser lid, metalwork on riser installed. Final erosion control completed, construction finished.
Beaver Creek Dam Rehab