Public and Capital Improvement Projects

From road improvements to new facilities, the City of Edmond is continuously adding and improving public amenities.

Please Note: This project list is not exhaustive. If you have questions about a project that is not on this list, please contact the City Manager's Office (405) 359-4500. For more immediate updates on street closures and other project impacts follow the City of Edmond on social media or check City Source  here on our website .

Currently Under Construction (16)

Updated Quarterly

33rd Street Water Tower

33rd Street Water Tower. Click to expand.

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

33rd Street Waterline Project

33rd Street Waterline Project . Click to expand.

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

AC Caplinger Baseball Fields - Hafer Park

AC Caplinger Baseball Fields - Hafer Park . Click to expand.

Point of Contact: Brad Raney, Director of Parks and Recreation Brad.Raney@edmondok.gov | (405) 216-7639

Broadway-Downtown ADA/Traffic Signal Improvements

Broadway-Downtown ADA/Traffic Signal Improvements. Click to expand.

Point of Contact: Leana Dozier, Downtown Transformation Manager | leana.dozier@edmondok.gov | 405-359-4601

Chisholm Creek Force Main Replacement

Chisholm Creek Force Main Replacement. Click to expand.

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

City Center Complex

City Center Complex. Click to expand.

Point of Contact: Leana Dozier, Downtown Transformation Manager | leana.dozier@edmondok.gov | 405-359-4601

Creek Bend Trail - Phase I

Creek Bend Trail - Phase I. Click to expand.

Point of Contact: Brad Moery, Senior Civil Engineer brad.moery@edmondok.gov | (405) 359-4771

Fire Station #6

Fire Station #6. Click to expand.

Point of Contact: Josh Hillis, Interim Deputy Fire Chief | 405-216-7306 | josh.hillis@edmondok.gov

I-35 Ground Storage Tank

I-35 Ground Storage Tank. Click to expand.

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Intelligent Transportation System Phase III

Intelligent Transportation System Phase III. Click to expand.

Point of Contact: Brad Moery, Senior Civil Engineer brad.moery@edmondok.gov | (405) 359-4771

Joint Use Library and YMCA

Joint Use Library and YMCA . Click to expand.

Point of Contact: Andy Conyers, Assistant City Manager of Administration | (405) 359-4728 | andy.conyers@edmondok.gov

Water Intake Structure

Water Intake Structure . Click to expand.

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Water Plant Expansion-Phase I & II: WTP-01B

Water Plant Expansion-Phase I & II: WTP-01B. Click to expand.

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Water Resource Recovery Facility Expansion (WRRF)

Water Resource Recovery Facility Expansion (WRRF). Click to expand.

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Water Transmission Line Staging Area

Water Transmission Line Staging Area. Click to expand.

Point of Contact: Kris Neifing, Director of Water Resources| 405-216-7696 | Kris.Neifing@edmondok.gov Background: This area will be used to store materials for the two phases of the Water Transmission Line Project and Intake Project. The City owned land at 2nd and Post Road will be used to store excess soil from the second phase of the water plant expansion. The project will result in savings of approximately $1.2M and avoid over 10,000 trucks from entering the road.

Water Treatment Plant Transmission Lines

Water Treatment Plant Transmission Lines. Click to expand.

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

33rd Street Water Tower

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Background: This project replaces the current 33rd Street tower near 33rd and Broadway. It holds 2 million gallons of water and is similar in design to the two towers located on Danforth and Coffee Creek Road.

Cost: $10,056,000

Funding: The project is funded by a loan through the Oklahoma Water Resources Board. The loan will be paid back over a 30-year period through water use charges.

Anticipated Completion: Project completed in December 2024.

Monthly Update: The tower is now in service, and the contractor has completed all punch list items. The old 33 rd  tower has been taken offline and is no longer holding water. It will be removed once the cellphone provider is no longer on the tower. The project will be formally accepted by Edmond Public Works Authority on January 13, 2025.

33rd Street Waterline Project

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Background: The 24” waterline will run along 33 rd  Street from I-35 to Broadway. The upsized waterline will replace the existing 8-12” lines and allow a more stable pressure for the south side of the city. This project will also allow the new 33 rd  Street water tower to receive the water turnover needed to maintain water quality standards.

Cost: $8,797,925.00 (Phase 1) | $10,500,000 (Phase 2)

Funding: The project is planned to be funded by a loan through the Oklahoma Water Resources Board for the first phase and the second phase will be funded through an FAP loan through the State. The loans will be paid back over a 30-year period through water use charges.

Anticipated Completion: December 2025

Update for this Month:

Phase I: This phase of the project consists construction of waterline from Bryant to west side of I-35. A pre-construction meeting was held on December 2, 2024. Pipe procurement is in progress with pipe delivery expected in February 2025. Construction activities are expected to start in February 2025.

Phase II: This phase of the project consists of waterline construction from TWR-4 site to Bryant. Its alignment is being finalized and the project is expected to bid on Spring 2025.

AC Caplinger Baseball Fields - Hafer Park

Point of Contact: Brad Raney, Director of Parks and Recreation Brad.Raney@edmondok.gov | (405) 216-7639

Background: The City selected Halff & Associates to develop a masterplan for AC Caplinger Sports Complex. The previous master plan was put out for bid during the summer of 2022. However, in the review process, it was decided that the plans do not meet the current and future needs of City and youth baseball. After a 7-month design process, phase one of the construction by Crossland began with demolition and earthwork. The final bid package which includes all remaining elements of the construction is now posted for public bid.

Improvement highlights include:

  • Four 11U/12U fields with bullpens
  • Six 7U/8U fields
  • Artificial turf infields with multiple basepath lengths
  • Covered dugouts
  • Covered bleachers
  • Picnic shelters & play areas
  • Parking lot upgrades
  • Paved walkways

Cost: $17.5 Million

Funding: 2017 Capital Improvement Tax Fund

Anticipated Completion: Late Fall 2025

Monthly Update: A groundbreaking ceremony was held September 10, 2024. Crossland construction has finished the installation of silt fence and construction fence on the perimeter. Tree demolition has commenced. Demolition and earthwork will occur over the next 3 months. The final bid package is currently posted to the public and anticipated to be awarded in January at a City Council meeting.

Broadway-Downtown ADA/Traffic Signal Improvements

Point of Contact: Leana Dozier, Downtown Transformation Manager | leana.dozier@edmondok.gov | 405-359-4601

Background: This project is the first in six intersection and sidewalk improvements that will create wider, safer curb ramps, put in place more prominent crosswalk markings, replace existing traffic signal cabinets and provide new audible pedestrian push buttons. The intersections scheduled for improvements include First Street, Main Street, Hurd Street, Campbell Street, Edwards Street and Ayers Street.

Work will take place one intersection at a time and construction will not close traffic on cross streets. Traffic signal work will occur only on Sundays, and project work will be scheduled so it will have as minimal as possible impact on planned events like Heard on Hurd or the Arts Festival. 

Cost: $1,850,000

Funding: The project is funded by funds awarded through the American Rescue Plan Act (ARPA).

Anticipated Completion for All Intersections: Summer 2025

Chisholm Creek Force Main Replacement

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Background: The project will replace around 3.5 miles of 18-inch ductile iron pipe with 24-inch HDPE pipe. The project will allow to convey influent sewage from Chisholm Creek Lift Station (CCLS) to the Coffee Creek Interceptor (CCI).

Cost: $6,969,460

Funding: The project is funded by a loan through the Oklahoma Water Resources Board. The loan will be paid back over a 30-year period through wastewater use charges.

Anticipated Completion: TBD

Monthly Update: Material approvals and procurement are ongoing. Construction activities are anticipated to start in February 2025.  Construction is expected to be complete by August 2025.

City Center Complex

Point of Contact: Leana Dozier, Downtown Transformation Manager | leana.dozier@edmondok.gov | 405-359-4601

Background: A new City Hall, Municipal Court, and Parking Garage is being constructed downtown along Littler Avenue between 1st Street and Main Street. The new City Hall building  will be 2 stories in height, containing  new City Council Chambers as well as several city departments that are currently located in four different buildings. The parking garage will be located on the site of the previous Planning and Public Works Building (10 S. Littler).  This same footprint will be the new municipal court building. The parking garage will be large enough to serve not only the needs of City employees, but also provide public parking for a growing downtown.

Architectural services with Rees have been ongoing since July 2022. In December, Flintco was selected as the Construction Manager at Risk and oversees all aspects of construction. This process is creating a more cohesive project team, expediting the construction, and allowing for more precise cost estimation throughout design.

An oversight committee consisting of Mayor Darrell Davis, Councilmember Tom Robins, City Manager Scot Rigby, City Engineer Steve Lawrence, Assistant City Manager Randy Entz, Assistant City Manager Andy Conyers, and Downtown Transformation Manager Leana Dozier is serving as a recommending body to the full City Council. The oversight committee has been directly involved in the project through completion.

Another potential future component of this project is geared towards economic development. City staff is exploring options for the four buildings and parcels that the City will be vacating. Prior to any action being taken, the City Council will discuss options in a public meeting and ultimately provide direction to staff.

Cost: Design - $2,000,000 | Construction -$44,000,000

Funding: The design will be paid for out of proceeds from the 2000 Capital Improvements Sales Tax. The money for construction of the three structures will be financed with repayment coming from the 2000 Capital Improvement Sales Tax.

Anticipated Construction Substantial Completion: March 2025

Monthly Updates: (as of December 17, 2024)

City Hall (Area A)

  • Items Completed: Metal Paneling
  • Ongoing Work: Drywall on both levels, tape and bedding in the stairwells and both levels, electrical and fire protection, windows and elevator installation    
  • Looking Ahead 6-Weeks: Drywall on both levels will be complete in two weeks, tape and bedding will be completed in four weeks, painting and tiling will begin after the new year, elevators will be completed in two weeks, and millwork will begin mid-January

Municipal Court (Area B)

  • Items Completed: Metal Paneling
  • Ongoing Work: Framing, plumbing, electrical, HVAC, windows, masonry and metal paneling  
  • Looking Ahead 6-Weeks: Drywall will be complete in 2 weeks, painting and tiling will begin mid-January

Parking Garage (Area C)

  • Items Completed: Glazing at the stairwells
  • Ongoing Work: Dumpster enclosure masonry, exterior framing and electrical  
  • Looking Ahead 6-Weeks: Elevator installation will begin mid-January, masonry will be completed by the end of the year.

Main Street Reconstruction

  • Items Completed: Paving complete
  • Ongoing Work: Striping

Creek Bend Trail - Phase I

Point of Contact: Brad Moery, Senior Civil Engineer brad.moery@edmondok.gov | (405) 359-4771

Background: In 2017, the City of Edmond was awarded a Transportation Alternative Program (TAP) grant from the Oklahoma Department of Transportation (ODOT) for the Creek Bend Trail, a 1.2 mile multi-use trail to connect the Spring Creek Trail, on the west side of I-35, 1/2 mile south of Second Street, to Coltrane Road.  This trail was shown on the 1999 Edmond Trails and Sidewalk Master Plan, the Bicycle Master Plan and now shown on EdmondShift as part of the core trail network. The trail will be constructed in two phases in order to immediately utilize the grant funding. The first phase is the ends of the trail (Phase I East and Phase I West). The city is actively working to acquire the two remaining parcels that would allow the full trail to be constructed. Once those parcels are obtained construction will soon follow on Phase II. 

1.2 miles from west side of Spring Creek Trail to Coltrane. ACOG funding is being provided.

Cost: $1,100,000. ACOG/ODOT Grant: $600,000

Funding: CIP and partially grant funded.

Anticipated Completion: Fall 2024

Update for this Month: Currently City staff is still working on the land acquisition for a small part of the Phase 2 portion of the Creek Bend Trail. Difficulties with obtaining land and/or easements is what caused us to break the project into 2 phases to allow the ODOT funds to be expended. Staff and Oklahoma Department of Transportation (ODOT) have put all portions of this trail on land that the COE currently owns or has easements for in the Phase 1 project. The remainder of the trail will be included in Phase 2.

Work began in early February 2024. The contractor has completed the majority of the construction on both the east and west portion of the trail. Striping and site work are the main items remaining to be complete before a punch list is created.

No further update for December 2024.

Fire Station #6

Point of Contact: Josh Hillis, Interim Deputy Fire Chief | 405-216-7306 | josh.hillis@edmondok.gov

Background: Fire Station #6 will be located at the corner of N Kelly Ave and Kelly Lakes Pass. Station #6 is the first station to be added since 2005. Edmond's population has increased by almost 20,000 people in the last twenty years. The land was purchased in 2007 and the city is excited to build another station that will improve the quality of its services. When this station is operational, the city will significantly improve coverage in NW Edmond, reducing travel times for fire response teams from approximately 4-8 minutes to 1-4 minutes in that district.   

Cost: $7,490,000 (Construction)

Funding: This project is being funded by Fire Department Reserves

Anticipated Completion: Summer 2025

Update for this Month: The steel structure is about 80% completed. The interior walls continue going up and the roof decking is near complete. The block walls and the interior steel studs are 60% installed. The retaining wall has begun going up and is approx. 40% complete.

I-35 Ground Storage Tank

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Background: This project is needed to balance the storage and pumping from the Water Plant to the Water Distribution system. The project will accommodate the new transmission lines from the Water Plant and allow the system to be more resilient in case of emergencies.

Cost: $28,429,266.00

Funding: The project is planned to be funded by a loan through the Oklahoma Water Resources Board. The loan will be paid back over a 30-year period through water use charges.

Anticipated Completion: February 2027

Monthly Update: Preliminary construction activities have started. The contractor (Archer Western) started erosion control work and site clearing and will begin to mobilize to the project site the week of October 28, 2024.

No further update for December 2024.

Intelligent Transportation System Phase III

Point of Contact: Brad Moery, Senior Civil Engineer brad.moery@edmondok.gov | (405) 359-4771

Background: This project consists of installing fiber optic cable and replacing the traffic signal cabinets and controllers and associated signal equipment at 22 intersections on 15 th  Street from Santa Fe to I-35; on Kelly from south City limits to Robin Hill; and on Santa Fe from 15 th  to Danforth. These intersections will connect to the Traffic Management Center via fiber optics and wireless communication network to improve traffic safety and mobility. Oklahoma Department of Transportation (ODOT) awarded the project on December 6, 2021, to Traffic Lighting Systems. Due to supply chain issues contractor did not mobilize until May 3, 2022.

Cost: $11,260,000

Funding: ODOT: $7,435,000. City Portion: $3,825,000. from the 2000 Capital Improvement Sales Tax Fund

Anticipated Completion: Fall 2024

Monthly Update: The contractor has completed work at all 22 intersections. City Staff has inspected all 22 intersections and 3 school cabinets and has provided a punch list to the contractor. The contractor is currently addressing punch-list items. When all items have been addressed, City Staff will verify the successful completion of this project.

No further update for December 2024.

Joint Use Library and YMCA

Point of Contact: Andy Conyers, Assistant City Manager of Administration | (405) 359-4728 | andy.conyers@edmondok.gov

Background: This project is a three-way partnership between the City of Edmond, the Metro Library System and the YMCA of Greater Oklahoma City. The need has arisen for this joint use building because the Edmond library is the busiest branch in the state and the YMCA is seeking to fill more needs in the community by operating a facility that is closer in size to the Mitch Park YMCA (which is the busiest of the 14 branches in the Greater OKC area). The success of the Mitch Park YMCA and Edmond Center Court has proven that when resources are pooled the community wins.

This facility will be located along 15th Street just east of I-35 on land previously owned by Henderson Hills Baptist Church. The location is near the geographic center of Edmond and was chosen to serve the community as the population continues to expand east of I-35. Additionally, Henderson Hills further strengthens the partnership by allowing a shared entrance off of 15th Street and use of an existing parking lot.

Cost: $3,850,000 (Land), $3,120,000 (Design), $31,640,000 (Construction Budget: $30,000,000 City, $1,500,000 YMCA, $140,000 Library)

Funding: The City of Edmond will pay for the land, full up-front cost of the design and the majority of the cost to construct the building. On the design, the city will pay the proportionate share to design the parts of the building that are directly tied to the Metro Library System, public meeting space, and half of YMCA part of the building (~$2M). The city will pay for half of the construction of the YMCA side of the building and the YMCA will reimburse the city for half of their side of the construction and decide of the building over the life of long-term lease agreement. It’s anticipated the total dollar amount due back to the city will be $12M.

The Metro Library System and YMCA will be responsible for the operation of their portions of the building.

Anticipated Completion: Early 2026

Update for this Month: A groundbreaking was held on the morning of August 8th. Clearing and grubbing of the site is complete. Currently, site utility work and the pouring of the basement floor and walls is occurring. Its anticipated construction will last for 18 months and conclude in early 2026.

No further update for December 2024.

Water Intake Structure

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Background: This project will replace the existing pump station below the dam and a new intake structure is proposed to be built near the NE corner of the lake.

Cost: $66,425,000

Funding: The project is funded by two loans through the Oklahoma Water Resources Board. The loans will be paid back over a 30-year period through water use charges. 

Anticipated Completion: February 2026

Intake Shaft: Contractor has completed all three tunnels into the lake. The contractor has completed work on air burst and chemical piping within the tunnel pipes along with gate installation for tunnel isolation from the shaft. The beams for the foundation of the pump station were placed and work on the foundation and above ground work on the pump station will be underway for the next several months including electrical, mechanical, HVAC, plumbing and masonry work. Electrical work for the ductbanks under the slab of the pump station is nearly complete.

Underwater Excavation-The contractor is complete with underwater excavation and the new buoy system has been put in place. The only work left to complete in the water is placing the T-screens in the lake.

Raw Water Lines: The contractor has been working on the installation of the two new 48-inch raw water lines that will convey raw water from the intake site to the water treatment plant.

Water Plant Expansion-Phase I & II: WTP-01B

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Background: The Water Plant project is split into three separate projects to expand treatment capacity from 12 Million Gallons Per Day (MGD) to 30 MGD and will have the ability to expand to 65MGD through future upgrades. . The first project started in August 2020 to increase the solids handling of the Water Plant, which allows spent lime from the treatment process to be reused for agricultural purposes. The second phase of the project was awarded in April 2022 to increase the electrical infrastructure redundancy and resiliency for the water plant expansion such as generators, and includes a new high lift pump station, finished water storage, granular activated carbon filters, and new backwash basin/pump station. The third phase of the project will complete the Water Plant Expansion Project and includes the ozone treatment, lime softening process, mixed media filters and chemical feed process.

The April 2022 update to the revised water plan is posted on www.edmondwater.com and has more detailed information on the water projects going on throughout Edmond. Cost: Phase I-$38,174,538 Phase II-$191,898,860.62 Phase III - TBD Funding: The projects are funded by loans through the Oklahoma Water Resources Board. The loans will be paid back over a 30-year period through water use charges. This project has also received a $12.5M American Rescue Plan Act Grant from the State which will reduce the cost of the project paid by our Customers. Anticipated Completion:

Phase I - Completed

Phase II - February 2027 Status: Phase I - The punch list is complete and the project is being closed out.   

Phase II:

High Lift Pump Station: Work continues at the new high lift pump station with the piping inside the structure which will continue for the next year. The electrical, mechanical, masonry and roofing work has continues including the installation of the roof system.

Granular Activate Carbon (GAC) Filter Complex: The granular activated carbon (GAC) filter building slab and the walls to enclose the structure are completed. Effluent piping is currently being installed. The GAC filters are to help reduce the potential for disinfection byproducts that form when chlorine is added to the water.

Clearwells: Both 4 million gallon clearwell tanks are nearly complete. The tanks have been partially filled for leak testing and placed in standby until they are ready for use. The contractor continued work on the clearwell distribution structure and that work will continue through the end of the year. 

Backwash Tower: The backwash tower is nearly complete on the exterior portion and will have one more coat of paint. Interior piping is underway and will be complete of the next few months.

Electrical and Emergency Generator Building: The electrical and emergency generator building is well underway. The under-slab conduits and structure for the generator pads has been placed in addition to electrical vaults surrounding the structure.  The generators are expected to be placed before the end of December.

Recycle Pump Station:  Wet well has been leak tested and the masons have started laying up CMU for the walls. The contractor has started pouring the slab for the associated backwash basin.

New Meter Vault: Construction of the new meter vault that will be handling the flow coming out of the water treatment plant is continued. Finished water lines to the meter vault was started.

Water Resource Recovery Facility Expansion (WRRF)

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Background: NE corner of Danforth and Midwest Blvd., designed to increase wastewater treatment capacity from 6 million gallons per day (MGD) to 12 MGD and comply with new requirements from the ODEQ/EPA.

Cost: $171,323,000

Funding: The projected was funded through revenue bonds and will be paid back over a 30-year period through Wastewater user charges.

Anticipated Completion: January 2025

Status:

Aeration Bains/Blower Building - The third of four aeration basins was put online this summer and is operating successfully. The fourth basin will be put online in the next couple of months as time allows.

Site work - Site grading is continuing to be finalized in several areas with sod being placed. The contractor completed installation of gabion baskets at Stormwater Pond No. 1. The contractor has installed fencing along the ease and south sides of the plant site.

Backup Generators - The emergency generators have been placed in service and are operational.

Solids Handling - Only punch list items remain on this process. It is functioning normally and in compliance.

Disinfection Process - The new UV system is in service and the existing disinfection system has been removed from service in preparation of demolition. 

Overall construction is 95% complete.

Water Transmission Line Staging Area

Point of Contact: Kris Neifing, Director of Water Resources| 405-216-7696 | Kris.Neifing@edmondok.gov Background: This area will be used to store materials for the two phases of the Water Transmission Line Project and Intake Project. The City owned land at 2nd and Post Road will be used to store excess soil from the second phase of the water plant expansion. The project will result in savings of approximately $1.2M and avoid over 10,000 trucks from entering the road.

Future uses of the site will be determined through a public process once the area is no longer being used for storage. The property will have a 60’ tree buffer on the north and east side.

Cost/Funding: Credit from the Second Phase Water Treatment Plant Project ~$1.2M Anticipated Completion: December 2027 Monthly Update: The site will be used for the I-35 Bridge construction and 80,000 yards of dirt will be hauled off site. Manhattan Construction was awarded that contract and more details to come.

The Main-03 project will start this fall and it will also be used as a site to store material until the project is complete in 2027.   

No further update for December 2024.

Water Treatment Plant Transmission Lines

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Background: This project is needed to move raw water from Arcadia Lake Intake to the new Water Treatment Plant and to send treated water from the new Water Treatment Plant to the entire City of Edmond. The raw water lines from the Intake will be corrosion resistant 48” HDPE and the Treated water transmission lines will be 42” and 36” from the Water Plant to I-35 & 2 nd  Street area.

Cost: $53,576,197

Funding: The project is being funded by a loan through the Oklahoma Water Resources Board. The loan will be paid back over a 30-year period through water use charges.

Anticipated Completion: February 2027

Monthly Update: The contractor (McKee) completed initial staking and started clearing and grubbing activities. The contractor has mobilized equipment to the construction laydown area and has built a road to access the laydown area.

Powered by Esri


Projects Under Design (12)

Updated Quarterly

ADA Sidewalk Improvements Along 2nd Street From 1-35 to Santa Fe Ave

ADA Sidewalk Improvements Along 2nd Street From 1-35 to Santa Fe Ave . Click to expand.

Point of Contact: Phil Jones, Sustainability Planner/ADA Coordinator Phil.Jones@edmondok.gov | (405) 359-4518

Charles D. Lamb Nature Preserve

Charles D. Lamb Nature Preserve. Click to expand.

Point of Contact: Frank Hale, Program Manager of Parks & Recreation | 405-359-4778 | Frank.Hale@edmondok.gov

Coffee Creek Interceptor Phase II

Coffee Creek Interceptor Phase II. Click to expand.

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

College Water Tower TWR-5

College Water Tower TWR-5. Click to expand.

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713| Will.Huggins@edmondok.gov

Danforth Water Tower Relocation Project (TWR-3A)

Danforth Water Tower Relocation Project (TWR-3A). Click to expand.

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Hunter's Creek Interceptor

Hunter's Creek Interceptor . Click to expand.

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Intersection Improvements at 2nd and Boulevard

Intersection Improvements at 2nd and Boulevard . Click to expand.

Point of Contact: Brad Moery, Senior Civil Engineer brad.moery@edmondok.gov | (405) 359-4771

Intersection Improvements at Danforth and Kelly

Intersection Improvements at Danforth and Kelly . Click to expand.

Point of Contact: Brad Moery, Senior Civil Engineer brad.moery@edmondok.gov | (405) 359-4771

Pelican Bay Aquatic Center Renovation

Pelican Bay Aquatic Center Renovation. Click to expand.

Point of Contact: Brad Raney, Director of Parks and Recreation Brad.Raney@edmondok.gov | (405) 216-7639

Route 66 Trail Connector

Route 66 Trail Connector . Click to expand.

Point of Contact: Brad Moery, Senior Civil Engineer brad.moery@edmondok.gov | (405) 359-4771

Spring Creek Interceptor Phase I

Spring Creek Interceptor Phase I . Click to expand.

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Water Plant Expansion - Phase III

Water Plant Expansion - Phase III. Click to expand.

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

ADA Sidewalk Improvements Along 2nd Street From 1-35 to Santa Fe Ave

Point of Contact: Phil Jones, Sustainability Planner/ADA Coordinator Phil.Jones@edmondok.gov | (405) 359-4518

Background: Improvements along this 5.4 mile corridor will include upgrades to out of compliance sidewalks/ramps, signalized intersections, and sidewalk/driveway cross-slopes. Design began in April 2021 (Kimley-Horn) and final design is on hold as other relevant construction has been occurring along this corridor.

Cost: $4,200,000. ODOT: $2,100,000. City: $2,100,000

Funding: $2.14M grant through ACOG/ODOT (STBG-UZA) and the remaining will be funded through the CIP.  Fortunately, on this grant we have 3 years to obligate funds and get it on a letting – no later than the end of FFY25 (ends in October).  We should have all easement data to ODOT by July 1, 2025.

Anticipated Completion: ODOT completed the NEPA review and the City needs to obtain 55 easements where the sidewalk does not fall in the right-of-way. In February 2024 the City will send out another letter on City of Edmond letterhead to the remaining property owners that have not been granted an easement, again providing information about the project. In June 2024 Poe & Associates will send out a third round of letters with the easement documents. We have extended the time to acquire easements to six more months, roughly the end of August. In September 2024 the period for acquiring easements will be closed and we’ll proceed with finalizing the 100% plans from Kimley-Horn.  It will likely be Spring before the ODOT bids the project in 2025. 

Monthly Update: On November 21 st , 2023 the City Engineering Department sent out a letter through Poe & Associates to property owners where the City still requires an easement, explaining the shared responsibility for sidewalks as indicated in municipal code 14.08.010.  On 2/26/2024, City Council approved 28 easements.  On 5/28/2024, City Council approved 7 more easements. On 10/14/2024 City Council approved 2 more easements, and since, 3 more easements have been signed by the owners. 5 eligible easements are remaining.  2 owners have decided not to sign at this point. Poe & Associates have been persistent in its efforts to get property owners to respond. 5 more easements are on the agenda for December 9 th , 2024 and 5 eligible easements are remaining.  A determination among staff for moving forward without the remaining properties will be made in December.  

No further update for December 2024.

Charles D. Lamb Nature Preserve

Point of Contact: Frank Hale, Program Manager of Parks & Recreation | 405-359-4778 | Frank.Hale@edmondok.gov

Background: Citizens asked the city to purchase approximately 22 acres of land adjacent to Hafer Park and partner with the Edmond Land Conservancy to create a conservation easement on the property.  The goal is to create the Charles D. Lamb Nature Preserve that includes a pedestrian bridge from Hafer Park, trails, and an outdoor classroom.

Cost: $1,700,000 estimate

Funding: In 2021, Edmond voters approved a temporary 0.25% sales tax to purchase the land, with any excess funds used for improvements. 

Anticipated Completion: It is difficult to project a completion date since we are grant dependent and cannot begin construction until grants are decisioned. 

Monthly Update: Most of the design process has been completed.  An updated Memorandum of Understanding was approved and Edmond submitted grant requests in January 2024 to assist with construction costs.  The land survey and preliminary trail marking were completed in February.  Site restoration can occur pre-construction and will begin in the next couple of months. 

Coffee Creek Interceptor Phase II

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Background: The project will upsize around 25,000 linear feet of the Coffee Creek Interceptor and spans from half a mile west of Sonner Rd to Brookhaven Park and to half a mile west of Bryant. This project will replace the sewer interceptor to make it capable of serving the fully developed sewer shed in a more resilient manner.

Cost: $24,000,000 estimate

Funding: The project is planned to be funded by a loan through the Oklahoma Water Resources Board. The loan will be paid back over a 30-year period through wastewater use charges.

Anticipated Completion: TBD

Monthly Update: The project is at 60% design and easement acquisition is underway. The project is expected to bid once easements are acquired.

No further update for December 2024.

College Water Tower TWR-5

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713| Will.Huggins@edmondok.gov

Background: This project will replace the current 500,000-gallon water tower with a 2 million-gallon elevated tower. The design will be similar to the other towers recently constructed on Danforth and Coffee Creek Road. The project will also remove the 70-year-old ground storage tank that is past its useful life.  

Cost: $12,000,000 estimate

Funding: The project is planned to be funded by a loan through the Oklahoma Water Resources Board. The loan will be paid back over a 30-year period through water use charges.

Anticipated Completion: TBD

Monthly Update: The design consultant submitted the 90% design deliverable on November 8, 2024. Staff completed the review of the submittal and help a review workshop with the consultant on December 9, 2024.  The project is expected to bid in Spring 2025.     

Danforth Water Tower Relocation Project (TWR-3A)

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Background: This project will relocate the current 500,000 gallon water tower located at the Danforth Pump Station to the NE complex site located at the corner of Sorghum Mill Rd and Linberg Ln. This project will increase distribution reliability, boost pressure, and add additional storage capacity to meet system requirements in this area of the city. It will also offset the need for a new 2 million gallon tank for the next 5 to 10 years.

Cost: $7,000,000 estimate

Funding: The project is planned to be funded by a Financial Assistance Program loan through the Oklahoma Water Resources Board.

Anticipated Completion: 2026

Update for this Month: Easement acquisition is underway. The design consultant is progressing the 90% design.

No further update for December 2024.

Hunter's Creek Interceptor

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Background: The project will upsize around 5,800 linear feet (LF) of the Hunter’s Creek Interceptor spans from Coffee Creek Road Lift Station to Kelly/Coffee Creek Rd. This project will replace the sewer interceptor and make it capable of serving the fully developed sewer shed in a more resilient manner.

Cost: $10,000,000 estimate

Funding: The project is planned to be funded by a loan through the Oklahoma Water Resources Board. The loan will be paid back over a 30-year period through wastewater use charges. 

Anticipated Completion: TBD

No further update for December 2024.

Intersection Improvements at 2nd and Boulevard

Point of Contact: Brad Moery, Senior Civil Engineer brad.moery@edmondok.gov | (405) 359-4771

Background: Adding southbound dual left turn lanes and a separate right turn lane, a northbound right turn lane and a westbound right turn lane to increase intersection capacity. Design work began in October 2017. City is seeking funding assistance.

Cost: $7,185,000 estimate

Funding: 2017 Capital Improvement Tax Fund

Anticipated Completion: Right-of-way FY23/24, Utilities FY 24/25, Construction FY25/26

Monthly Update: This project will be paired with the Main and Boulevard intersection project due to the drainage being in the same basin and the same design engineer for both projects. Additional funding sources for this work are currently being investigated.

No further update for December 2024.

Intersection Improvements at Danforth and Kelly

Point of Contact: Brad Moery, Senior Civil Engineer brad.moery@edmondok.gov | (405) 359-4771

Background: Adding dual left turn lanes on each leg of the intersection and adding right turn lanes on Danforth and southbound Kelly. Addition of a raised center median. Sidewalk is being replaced along Danforth, west of Kelly. Design work is still ongoing. A new waterline project was recently awarded to a contractor in this area and will be installed as part of a separate project. If utility lines need to be moved, utility companies will submit plans to the city for review and approval, then they will start to relocate their utility lines.

Cost: Current estimate $8,978,439, Federal Share $7,182,751, City Share $1,795,688

Funding: 2000 Capital Improvement Tax Fund

Anticipated Completion: Utility Relocations budget FY24, Construction budget in FY24/25

Monthly Update: Staff has reviewed 90% plans and provided comments back to the consultant. This project is scheduled for Federal Fiscal 2025. This project is anticipated to be out for bid early 2025.

Consultant has created an exhibit showing the planned work that COE can distribute to citizens who signed up for the email update list and post on City website.

No further update for December 2024.

To view the exhibit for this project,  Click Here 

Pelican Bay Aquatic Center Renovation

Point of Contact: Brad Raney, Director of Parks and Recreation Brad.Raney@edmondok.gov | (405) 216-7639

Background: The Pelican Bay Aquatic Center has been a valuable community resource for nearly 25 years. However, the pool is beginning to show signs of wear, with notable issues such as significant leaking and settling of the concrete pool deck. Despite its age, the facility continues to earn local recognition and has seen increased attendance over the past four years. The upcoming renovation project aims to address these critical issues, ensuring the pool's longevity for another 25 years. Key elements of the renovation include a new concrete pool deck, the Myrtha Renovacation System (featuring a new pool liner and gutter system), ADA-compliant lifts and stairs, new play structures in the zero-depth-entry area and spray ground, refinishing of the steel pool slide supports, plumbing repairs, new main drains, and upgraded LED in-pool lighting. If additional funding allows, potential project alternates may include expanded parking and further ADA enhancements in the parking lot.

Cost: $7,000,000

Funding: 2017 CIP Tax

Anticipated Completion: Memorial Day Weekend of 2026

Update for this Month: GH2 Architects is leading the redesign of the facility. They have completed schematic design and are in the process of developing construction documents. It is anticipated that the bid will be posted to the public in early 2025 with construction beginning after the 2025 summer swim season.

No further update for December 2024.

Route 66 Trail Connector

Point of Contact: Brad Moery, Senior Civil Engineer brad.moery@edmondok.gov | (405) 359-4771

Background: 1.8 miles connecting Route 66 Trial to the Spring Creek Trail.

Cost: $3,000,000

Funding: 2017 Capital Improvement Tax Fund, ODOT Grant

Anticipated Completion: We hope to bid the project in early 2025. Construction schedule is not yet determined.  

Monthly Update: The Planning Department received a grant from Oklahoma Department of Transportation (ODOT) to support the construction of the trail. The grant funds will support the project; however, the City of Edmond will have to wait for the ODOT process to move forward. ODOT will work on an environmental assessment and then proceed with development of the trail.

This project will resume as soon as the US Army Core of Engineers completes their final review of the trail.  This will enable the consultant to pick up comments from the City, USACE, and ODOT and complete the design process.

Spring Creek Interceptor Phase I

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Background:

The project will upsize approximately 8,100 LF of sewer Interceptor from 24-inch to 36-inch/42-inch and begins from Spring Creek Lift Station and extending along the Spring Creek Floodplain to Coltrane/15 th  Street. This project will replace sewer interceptor so that it is capable of serving the fully developed sewer shed in a more resilient manner.

Cost: $15,000,000 estimate

Funding: The project is planned to be funded by a loan through the Oklahoma Water Resources Board. The loan will be paid back over a 30-year period through wastewater use charges.

Anticipated Completion: TBD

Update for this Month: The project is at 90% design phase, easement acquisition and environmental assessment is underway. The project is expected to bid once easement acquisition is complete.

No further update for December 2024.

Water Plant Expansion - Phase III

Point of Contact: Will Huggins, Senior Water Resources Engineer | 405-216-4713 | Will.Huggins@edmondok.gov

Background: The Water Plant project is split into three separate projects to expand treatment capacity from 12 Million Gallons Per Day (MGD) to 30 MGD. The first project started in August 2020 to increase the solids handling of the Water Plant, which allows spent lime from the treatment process to be reused for agricultural purposes. The second phase of the project was awarded in April 2022 to increase the electrical infrastructure redundancy and resiliency for the water plant expansion such as generators, and includes a new high lift pump station, finished water storage, granular activated carbon filters, and new backwash basin/pump station. The third phase of the project will complete the Water Plant Expansion Project and includes the ozone treatment, lime softening process, mixed media filters and chemical feed process.

The Water Plant Expansion project is being divided up into three projects as identified in the 2019 Revised Water Master Plan. Once all three phases of water plant expansion are complete we will be capable of producing 30 Million Gallons Per Day (MGD) and will have the ability to expand to 65MGD through future upgrades. The July 2023 update to the revised water plan is posted on  www.edmondwater.com  and has more detailed information on the water projects going on throughout Edmond.  

 Cost: $280MM to $300MM (estimated)

Funding: The projects are funded by loans through the Oklahoma Water Resources Board. The loans will be paid back over a 30-year period through water use charges. This project has also received a $12.5M American Rescue Plan Act Grant from the State which will reduce the cost of the project paid by our Customers.

 Anticipated Completion: Design completion scheduled for November 2025.

Update for this Month: Staff met with the design consultant on November 8 th  and 13 th  to review the 60% design deliverable. The consultant is progressing the 90% design deliverable. The design is expected to be completed in late 2025.  


Recently Completed Projects (21)

Quiet Zones

Quiet Zones. Click to expand.

The new quiet zones went into effect winter 2020 at all 11 railroad crossings in the city. Signalization upgrades and medians were constructed to allow trains to sound their horns only in emergency situations, creating a more peaceful atmosphere for residents, visistors, and business owners. The quiet zones have also attracted new developments to the downtown area including the Edmond Railyard, Icehouse Project, and The Silos apartments. Downtown Edmond is projected to see more than $100 million in future development as a result of the project.

Relocation of Fire Station #2

Relocation of Fire Station #2. Click to expand.

The station has moved to the NW corner of 15th & Kelly. Its new location west of the railroad decreases response times and features modern facilities. The grand opening took place in early 2020.

Edmond Center Court

Edmond Center Court. Click to expand.

On the NE corner of 15th & Kelly, this project was made possible by a partnership between the City of Edmond and Edmond Public Schools. The Edmond Center Court was completed in 2020 and features 24 outdoor courts and six indoor courts.

Gracelawn Cemetery Expansion

Gracelawn Cemetery Expansion . Click to expand.

The city owned Gracelawn Cemetery was runnining out of of burial plots. To accommodate this need, the City Council purchased 21 acres directly north of the existing cemetery adding 1,500 in-ground plots, 1,200 columbarium niches, and a committal shelter. The project was completed in 2021.

Water Wells

Water Wells. Click to expand.

This project included drilling 20+ wells around the City. The construction for the first 10 began in April 2021. Other well sites are being permitted and will begin once permits are in place and the projects are bid.

Animal Services Shelter Expansion

Animal Services Shelter Expansion. Click to expand.

Approximately 45 additional kennels were added to the current 22 kennels to meet the current and future housing needs at the shelter. This project also includes a remodel of the current facilities so they better meet the operational needs of the shelter. The project was completed in October 2020.

Integris Trail

Integris Trail . Click to expand.

This quarter of a mile trail connects to Spring Creek Trail, near Arcadia Lake. A popular trail for birding, hiking, and road biking, it is now accessible by the Integris parking lot, located on the east side of the I-35 frontage road between 2nd & 15th. Construction began in September 2018 and the trail head opened in spring 2019.

Intelligent Transportation System Phase II

Intelligent Transportation System Phase II. Click to expand.

This project consisted of installing fiber optic cable and replacing the traffic signal cabinets and controllers and associated signal equipment at 22 intersections on portions of Broadway, Danforth, Covell, and Santa Fe. Those intersections are now connected to the existing Traffic Management Center via fiber optics and wireless communication network to improve traffic safety and mobility. Construction began in February 2019 and was substantially complete in November 2022.

Water Plant Control Building

Water Plant Control Building . Click to expand.

This building will house the Water Plant Operations and Well staff. The project will replace the current control building and was completed in 2022. The project was funded by a loan through the Oklahoma Water Resources Board. The loan will be paid back over a 20-year period through water use charges.

Traffic Signals I-35 & Covell

Traffic Signals I-35 & Covell. Click to expand.

This project consisted of widening the Northbound off ramp to Covell to increase capacity. Traffic signal lights were installed at the Northbound and Southbound on/off ramps on Covell. These signals were designed with the latest ITS technology and are connected to the Traffic Management Center.

Danforth Waterline

Danforth Waterline. Click to expand.

The 24” water line runs along Danforth from the existing Danforth Water tower/Soccer Fields to the UCO area. The upsized water line was installed to ensure that the downtown area maintains a more stable water pressure. The project was funded by a loan through the Oklahoma Water Resources Board. The loan will be paid back over a 30-year period through water use charges. 

2nd and Byrant Intersection

2nd and Byrant Intersection . Click to expand.

Named the top traffic concern area by a recent survey of Edmond citizens, the city added dual left turn lanes and separate right turn lanes on all four approaches to intersection.

KickingBird Golf Renovations

KickingBird Golf Renovations. Click to expand.

Total Cost: $20,338,472.48

Hafer Feeder 4524 Upgrade Phase II

Hafer Feeder 4524 Upgrade Phase II . Click to expand.

This project was the second phase of the upgrades to the overhead electric distribution circuits out of the Hafer substation. The project focused on two areas of Hafer Feeder 4524.  First, poles were replaced and a larger conductor was added to a section along 33rd Street from I-35 to Coltrane will have  

Arcadia Lake Masterplan

Arcadia Lake Masterplan . Click to expand.

Arcadia Lake has been operating and well loved since 1987. Arcadia Lake serves several major functional purposes as flood control and as a primary water source for the city, but also provides many recreational opportunities as well.

Feasibility Study for BNSF Pedestrian Crossing

Feasibility Study for BNSF Pedestrian Crossing. Click to expand.

The study will address pedestrian access between the recently approved multi-family development west of the BNSF railroad tracks and the downtown. The study will evaluate two possible locations where the underpass could be constructed. The study will address up to three construction methods: Jack-and-Bore, Liner Plates, and Cut-and-Cover. The actual method could be a combination of the three. Each method will evaluate ease of construction, construction cost, time of construction, operational impacts, and addressing soil conditions.

Stephenson Park and Streetscape Updates

Stephenson Park and Streetscape Updates . Click to expand.

One of the primary goals of the upgrades is for the park to be “passive” with more open space. Additional elements that are included in the upgrades: picnic tables, expanded event space, and a renovated pavilion. Design was amended to include regional detention of storm water run-off which will assist in future development of the area.

Smart Choice AMI Upgrade

Smart Choice AMI Upgrade. Click to expand.

This project replaced the existing electric and water meter endpoints with smart meters. The system is comprised of a communication system, an AMI head end, a meter data management system, and the electric and water meter endpoints. The communication system is a 900 MHz radio system comprised of 12 communication gateways and 92 routers throughout the City. This piece allows communications between the AMI head end and the metering endpoints. The AMI head end receives the daily reads from the meters, validates the readings and relays them to the meter data management system. The meter data management system then moves the meter readings to the existing billing system and provides appropriate data to other platforms.

Service-Blake Soccer Complex Renovations

Service-Blake Soccer Complex Renovations . Click to expand.

Splash Pad, Play Structure, and Accessibility Improvements at Ted Anderson Park

Splash Pad, Play Structure, and Accessibility Improvements at Ted Anderson Park . Click to expand.

In 2015, the Capital Improvement Advisory Task Force (Task Force) provided recommendations to City Council regarding capital improvements to be constructed by sales tax funds in the event that the half-cent sales tax that funded the Public Safety Center was extended. It was extended by a vote of the public in April 2016. One of the projects recommended to City Council, by the Task Force, was "Expand and Improved Park System with increased splash pad facilities".

Traffic Signal on Covell at Cheyenne Middle School

Traffic Signal on Covell at Cheyenne Middle School . Click to expand.

Work included signalizing the intersection and connecting to the Traffic Management Center via the existing fiber optics network on Covell. 

Quiet Zones

The new quiet zones went into effect winter 2020 at all 11 railroad crossings in the city. Signalization upgrades and medians were constructed to allow trains to sound their horns only in emergency situations, creating a more peaceful atmosphere for residents, visistors, and business owners. The quiet zones have also attracted new developments to the downtown area including the Edmond Railyard, Icehouse Project, and The Silos apartments. Downtown Edmond is projected to see more than $100 million in future development as a result of the project.

Total Cost: $4,000,000

Relocation of Fire Station #2

The station has moved to the NW corner of 15th & Kelly. Its new location west of the railroad decreases response times and features modern facilities. The grand opening took place in early 2020.

Total Cost: $4,300,000

Edmond Center Court

On the NE corner of 15th & Kelly, this project was made possible by a partnership between the City of Edmond and Edmond Public Schools. The Edmond Center Court was completed in 2020 and features 24 outdoor courts and six indoor courts.

Total Cost: $16,500,000. Edmond Public Schools: $9,500,000. City: $7,000,000 (City paid $2,500,000 for the land)

Gracelawn Cemetery Expansion

The city owned Gracelawn Cemetery was runnining out of of burial plots. To accommodate this need, the City Council purchased 21 acres directly north of the existing cemetery adding 1,500 in-ground plots, 1,200 columbarium niches, and a committal shelter. The project was completed in 2021.

Total Cost: $3,400,000

Water Wells

This project included drilling 20+ wells around the City. The construction for the first 10 began in April 2021. Other well sites are being permitted and will begin once permits are in place and the projects are bid.

Total Cost: $9,600,000

Animal Services Shelter Expansion

Approximately 45 additional kennels were added to the current 22 kennels to meet the current and future housing needs at the shelter. This project also includes a remodel of the current facilities so they better meet the operational needs of the shelter. The project was completed in October 2020.

Total Cost: $3,300,000

Integris Trail

This quarter of a mile trail connects to Spring Creek Trail, near Arcadia Lake. A popular trail for birding, hiking, and road biking, it is now accessible by the Integris parking lot, located on the east side of the I-35 frontage road between 2nd & 15th. Construction began in September 2018 and the trail head opened in spring 2019.

Total Cost: $427,000

Intelligent Transportation System Phase II

This project consisted of installing fiber optic cable and replacing the traffic signal cabinets and controllers and associated signal equipment at 22 intersections on portions of Broadway, Danforth, Covell, and Santa Fe. Those intersections are now connected to the existing Traffic Management Center via fiber optics and wireless communication network to improve traffic safety and mobility. Construction began in February 2019 and was substantially complete in November 2022.

Total Cost: $6,750,000. ODOT: $5,400,000. City Portion: $1,350,000.

Water Plant Control Building

This building will house the Water Plant Operations and Well staff. The project will replace the current control building and was completed in 2022. The project was funded by a loan through the Oklahoma Water Resources Board. The loan will be paid back over a 20-year period through water use charges.

Total Cost: $8,043,000

Traffic Signals I-35 & Covell

This project consisted of widening the Northbound off ramp to Covell to increase capacity. Traffic signal lights were installed at the Northbound and Southbound on/off ramps on Covell. These signals were designed with the latest ITS technology and are connected to the Traffic Management Center.

Total Cost: $1,750,000

Danforth Waterline

The 24” water line runs along Danforth from the existing Danforth Water tower/Soccer Fields to the UCO area. The upsized water line was installed to ensure that the downtown area maintains a more stable water pressure. The project was funded by a loan through the Oklahoma Water Resources Board. The loan will be paid back over a 30-year period through water use charges. 

Total Cost: $9,167,511

2nd and Byrant Intersection

Named the top traffic concern area by a recent survey of Edmond citizens, the city added dual left turn lanes and separate right turn lanes on all four approaches to intersection.

Total Cost: $7,500,000

KickingBird Golf Renovations

Total Cost: $20,338,472.48

KickingBird Golf Club celebrated its 50th Anniversary in May of 2021. The clubhouse opened in May of 1971 and besides a few additions to the building there were no changes. This project was intended to put KickingBird Golf in a successful position for the next fifty years. The new clubhouse includes a full-service restaurant and bar and a separate special events center to be used for events and meeting space. This project also included an indoor teaching facility, driving range pavilion, expanded short game practice area, and more parking. The Greens and Irrigation project included a complete reconstruction of all greens, laser leveling and sodding of all tee boxes, and a new irrigation system.

Hafer Feeder 4524 Upgrade Phase II

This project was the second phase of the upgrades to the overhead electric distribution circuits out of the Hafer substation. The project focused on two areas of Hafer Feeder 4524.  First, poles were replaced and a larger conductor was added to a section along 33rd Street from I-35 to Coltrane will have  

A larger conductor was installed in the second area, located south out of the Hafer substation through back lot easements in the Turtle Creek and Forest Oaks Phase 2 subdivisions before turning west in easements behind properties along Running Branch Road to Bryant Road.  Additionally, fourteen poles were added to accommodate the larger conductor.

These upgrades will improve the distribution system reliability and allow the use of the additional capacity provided by the substation transformers, which were upgraded in previous years. 

Total Cost: $2,500,000

Arcadia Lake Masterplan

Arcadia Lake has been operating and well loved since 1987. Arcadia Lake serves several major functional purposes as flood control and as a primary water source for the city, but also provides many recreational opportunities as well.

Over the last several years, the lake has seen an increase in visitors, which highlighted the need for improvements to its infrastructure and amenities. This comprehensive review and analysis by LandPlan Consultants of Tulsa will provide a path forward for Arcadia Lake. The Master Plan was approved by the Edmond City Council on August 28, 2023.

A full copy of the Master Plan with more information on the development process is available through the link below.

Total Cost: $251,998.50

Feasibility Study for BNSF Pedestrian Crossing

The study will address pedestrian access between the recently approved multi-family development west of the BNSF railroad tracks and the downtown. The study will evaluate two possible locations where the underpass could be constructed. The study will address up to three construction methods: Jack-and-Bore, Liner Plates, and Cut-and-Cover. The actual method could be a combination of the three. Each method will evaluate ease of construction, construction cost, time of construction, operational impacts, and addressing soil conditions.

Total Cost: Design - $72,300 Construction - $5,000,000 est.

Stephenson Park and Streetscape Updates

One of the primary goals of the upgrades is for the park to be “passive” with more open space. Additional elements that are included in the upgrades: picnic tables, expanded event space, and a renovated pavilion. Design was amended to include regional detention of storm water run-off which will assist in future development of the area.

Streetscape for 4th St, between Littler and Boulevard is part of the Stephenson Park plans. This block of 4th St. will be completely rebuilt. The design work includes on-street parking, trees and landscape, lighting, and a water line upgrade.

Total Cost: $6,862,580.75

Smart Choice AMI Upgrade

This project replaced the existing electric and water meter endpoints with smart meters. The system is comprised of a communication system, an AMI head end, a meter data management system, and the electric and water meter endpoints. The communication system is a 900 MHz radio system comprised of 12 communication gateways and 92 routers throughout the City. This piece allows communications between the AMI head end and the metering endpoints. The AMI head end receives the daily reads from the meters, validates the readings and relays them to the meter data management system. The meter data management system then moves the meter readings to the existing billing system and provides appropriate data to other platforms.

Total Cost: $13,842,482

Service-Blake Soccer Complex Renovations

The Service Blake Soccer Complex has been home to Edmond’s soccer programs for decades. With growing needs and an aging site, renovations were identified as a need for the complex. Early in the design phase, infrastructure improvements were identified as the number one need. The project includes demolition of the northwest concession/bathroom building, the maintenance buildings, and the southwest concession/bathroom building. We will replace each concession/bathroom building with new larger buildings with matching architecture, at similar locations. The new building will have modern features and allow for better customer service for the patrons needing concessions. The northwest building will also have offices and a larger conference room for coaches and/or tournament meetings. Also, the entrances will be beautified, and we will add a drop off lane for better traffic flow. Once complete this complex will be a standout among others, drawing high level tournaments and offering great league play.

Total Cost: Construction contract $5,170,000.00   

Splash Pad, Play Structure, and Accessibility Improvements at Ted Anderson Park

In 2015, the Capital Improvement Advisory Task Force (Task Force) provided recommendations to City Council regarding capital improvements to be constructed by sales tax funds in the event that the half-cent sales tax that funded the Public Safety Center was extended. It was extended by a vote of the public in April 2016. One of the projects recommended to City Council, by the Task Force, was "Expand and Improved Park System with increased splash pad facilities".

Staff evaluated existing park properties to determine the suggested location of Ted Anderson Park. Staff based this suggestion on criteria such as, distribution of swimming pool construction permits, available space, proximity to a suitable water supply, and sanitary sewer capacity.

 The project includes construction of a splashpad, restroom, and planting of additional trees. Additionally, the contract includes repairing and replacing existing sidewalks throughout the park to improve safety and accessibility of the space.

As a companion to this project, the entire play structure is being remodeled. The remodel will provide a new play structure and safety surfacing. Synthetic turf will replace the woodchips that were previously used for safety surfacing.

Total Cost: $1,088,706.00 for the Splashpad, restroom and accessibility improvements. $175,716.00 for the playground updates.

Traffic Signal on Covell at Cheyenne Middle School

Work included signalizing the intersection and connecting to the Traffic Management Center via the existing fiber optics network on Covell. 

Total Cost: $811,047