
495/90 Interchange Reconstruction Project
The I-495 and I-90 interchange project is one of Massachusetts’ largest and most complex transportation projects since the Big Dig.

The I-495 and I-90 interchange is one of the busiest in Massachusetts. It was also one of the most congested due to substandard geometry, weaving, and a bottleneck that funneled all cars through a defunct toll plaza, contributing to crash rates twice the statewide average. To enhance mobility and safety, the interchange critically needed geometric and operational improvements.
VHB’s team of scientists, planners, and engineers, in collaboration with our design-build partners Barletta Heavy Construction, O&G Industries, and Aetna Bridge Company, took an integrated approach to designing the interchange. The combined team is leveraging highway, traffic, and structural engineering professionals with years of experience in design-build projects while navigating complex environmental and regulatory requirements and conducting robust public outreach.
Our team developed a winning Alternative Technical Concept (ATC) that both addressed the transportation-related needs of the project and also dialed up the sustainability considerations. A key component of the ATC is that we eliminated three structures from the Base Technical Concept (BTC), saving the Commonwealth of Massachusetts time, money, and long-term maintenance concerns while also significantly reducing the embodied carbon footprint.
As of summer 2024, the design-build team hit a major milestone: Design for the interchange is now substantially complete.
Use the interactive map to the right to view the project in relation to the natural resources delineated by the VHB team.
Environmental
The I-495/I-90 interchange redevelopment project is situated among hundreds of acres of environmentally sensitive areas that include the Sudbury River and its watershed, vernal pools, and many acres of Atlantic White Cedar swamp—an endangered wetland habitat that is a haven for rare plant, animal, and insect species.
VHB began by physically mapping these areas using 3,600 wetland flags, then used HydroCAD and HEC-RAS technologies to model how the areas would be affected by changes to the interchange during and after construction. VHB’s design work comprised four major environmental considerations:
- Complying with environmental regulations and permit requirements
- Preserving wetland resources
- Managing stormwater
- Designing hydraulic systems
Our scientists and technicians monitored impacts on environmental areas through numerous final design iterations and development of construction staging packages, closely coordinating with MassDEP, MassDOT, and the construction team throughout. VHB’s extensive knowledge of Massachusetts’ environmental regulations, experience designing solutions to complex environmental challenges, and access to innovative technological tools equipped us to keep the project on track by complying with state and local environmental regulations while improving runoff conditions for more than 650 acres of roadway.
Our designers ultimately devised solutions that not only preserve the existing ecology but also establish new wetlands in some areas that had previously been paved—all while maximizing driver safety during and after storm events.
Case Study: Ramps EN and NE
The BTC for the ramps between I-495 northbound and I-90 eastbound bordered sensitive environmental resource areas, including an archaeological resource area, wetlands, an intermittent stream, and land that falls under Massachusetts Department of Conservation and Recreation Article 97.
VHB redesigned these ramps with an ATC that leaves more space between vulnerable areas and structures, allowing for over six acres of wetland restoration.
Because our ATC was only considered a minor change to the BTC, it did not require extensive review by regulatory agencies or permit amendments under the Massachusetts or National Environmental Policy Act (NEPA), minimizing the potential for project delays.
The ATC mitigates stormwater by reducing impervious cover (the result of eliminating three structures in the BTC) and meets Massachusetts environmental performance standards for bordering lands subject to flooding and stream crossings. It also pulls the proposed infrastructure further away from the archaeological resource areas.
Shown right: A 3D model of the proposed interchange, showing both overhead and driver viewpoints.
Highway
In the proposal phase, VHB developed a 3D model of the project to map proposed alignments and evaluate their temporary and permanent impacts on the surrounding area and its environmental resources. Using model-based design software, we created a 3D rendering of the interchange, allowing VHB and MassDOT to digitally evaluate and visualize alternatives.
Ultimately, VHB’s design included 13 total alignments—encompassing I-90 eastbound and westbound, I-495 northbound and southbound, Fruit Street (which runs over I-495 adjacent to the interchange), and eight ramps in between the two highways—to realize the final interchange configuration envisioned by the BTC and our added-value ATC.
Our designs, including our approved ATC, improved the alignments, reduced profiles and wall heights where necessary, optimized structure depth, and minimized impacts to wetland resource areas while still maintaining minimum vertical clearances between roadways and railroads.
Highway designs also included guardrail, retaining wall profiles, side slope grading, drainage, and grass swales.
Shown Right: Designs showing elevations and traverse sections for some of the structures.
Structures
This monumental project includes 12 bridges and 32 walls. Beginning in the proposal phase, the design-build team proposed several enhancements to the BTC to increase the structures’ lifecycles, reduce costs, and minimize environmental impacts. The result will be new direct, semi-direct, and loop ramp configurations. This table summarizes the enhancements our winning ATC proposed:
Some highlights from construction ⬇
Shown below: Partial construction of the bridge that carries I-495 NB over I-90.
Recently constructed pier and abutments supporting the two-span continuous girders, prior to the deck being placed.
Aerial view of the bridge that carries I-495 NB over I-90, showing girders and SIP forms.
Shown Right: Temporary Ramp WN trestle under construction.
Case Study: Ramp WN
To minimize temporary and permanent impacts to the wetland over which Ramp WN runs, the design team adjusted the span lengths of the bridge carrying Ramp WN to eliminate a bridge pier within the wetland.
VHB and its design team partners also developed an innovative seismic analysis methodology for Ramp WN. The BTC lacked subsurface information in the wetland resource area where Ramp WN was proposed to be constructed due to access constraints, and the design-build team was unable to collect this information until the trestle required to construct Ramp WN was in place. Once acquired, the subsurface information revealed poor soil conditions that were significantly different than the surrounding information. These conditions are not typically found in Massachusetts.
Given the long length of the structure and differing seismic site classes along its length, the design team had to develop an alternate method to complete the seismic analysis of the Ramp WN structure. This included developing a site-specific response curve that intentionally considered the predicted behavior of the poor soils at the proposed location of two wetland piers. This made certain that the structure would withstand potential future earthquakes and allowed the project to advance.
Ramp WN
Shown Right: Conceptual animation of the construction of Ramp WN.
(cont.) Case Study: Ramp WN
As shown in the animation to the right, VHB's design for Ramp WN comprised four construction stages, beginning with the development of a temporary trestle bridge for access over the swamp. This temporary bridge allowed the design-build team to first collect subsurface information that informed the ultimate design. The next stage was to bring construction vehicles onto the temporary trestle to build the ramp foundation. As shown right, once the foundation is complete, the bridge superstructure is built from the trestle. Finally, the temporary trestle is removed.
Shown right: Initial Traffic Staging Plans.
Traffic Management
To minimize the project’s impacts on drivers traveling through the interchange, MassDOT required the team to maintain three lanes in each direction on the I-495 and I-90 mainlines during peak travel hours, while also maintaining all ramp connections between I-495 and I-90 throughout construction. This presented the design-build team and VHB’s traffic engineers with the complex task of facilitating travel and construction simultaneously throughout the project’s five major construction stages.
To do so, VHB’s traffic engineers collaborated with our construction partners and designed temporary lane shifts, a temporary crossover of I-495 southbound, temporary ramp alignments, temporary barriers between travel lanes and the work zone, and new signage and pavement markings for shifted mainline lanes and ramps to help maneuver traffic safely through the project area.
We also planned access and egress points for construction staff, equipment, and materials to safely access and egress the work zone. All temporary traffic controls are supported by a Real-Time Traffic Monitoring (RTTM) system that provides travel time and speed information to the traveling public.
Design-Build Team
Public Engagement
Throughout the project, VHB and the design-build team have had an integral role in liaising with the public affected by the work. We create and present content for all public meetings, legislative briefings, and the 495/MetroWest Partnership. This work has helped to build relationships with project abutters and increase local support for the project, paving the way for greater public satisfaction with MassDOT. It has also helped MassDOT avoid unnecessary obstacles from local opposers to the project.
VHB's Design-Build Experience
For more than 20 years, VHB has been a leader in delivering complex design-build transportation projects, designing high-profile roadway, bridge, transit, and rail improvements along the East Coast, and consistently providing high-quality, innovative, and timely design and construction services. See a timeline of our design-build projects through the years.
VHB also supports clients firmwide by serving as the preliminary designers developing BTCs and RFPs, creating department of transportation manuals and trainings, serving on selection committees, and reviewing design-build team submittals. Throughout this project, as with all design-build projects, our team has collaborated closely with the owner (MassDOT) and our construction partners at every step.
This broad experience provides us with a deep understanding of clients’ concerns and focus areas. From inception to completion, our extensive team of professionals has the knowledge and experience to effectively deliver design-build services and mitigate risk throughout the process. Our one-firm approach allows us to respond to the intense staffing demands of design-build projects by leveraging talent from across our footprint to complement in-the-field support.
495/90 Project Leaders
Connect with our Alternative Delivery Team ⬇ on LinkedIn or learn more about VHB's Alternative Delivery service offerings on our website: Alternative Delivery | VHB
Deck placement of I-495 bridge over railroad