Managing Seabrook Island's Dynamic Shoreline
History of Beach Management Projects on Seabrook Island
Shoreline Change
Since 1980, around 22 percent of shoreline on Seabrook Island has gained over 1000 ft of beach or dune width. Soft engineering solutions have buried all but 2500 linear feet of seawall and added upward of 100 acres of beach/dune/beach trust habitat. Seabrook Island POA has sponsored annual monitoring surveys of the beach and uses this information to plan future beach management projects.
Ariel Photos of Beach from 1979 and 2022
Timeline
1948
Capn Sams Inlet breaches Kiawah Split, creating multiple channels. A single channel becomes dominant by early 1950s.
1963
Mouth of Capn Sams Inlet is aligned with the mouth of Capn Sams Creek, becoming the model for inlet relocations.
1970
Seabrook Island becomes a planned unit development. Roads, golf course and lots are plotted and used as a basis for a development plan. Seabrook Island is in a rapid erosion cycle with some areas of beach losing over 20 ft/yr.
1973
Beach Club is under construction and impacted by erosion. First shore-protection measures (seawall) consisting of sandbags, sandbag groins and sheet-pile bulkheads are used.
1975-1981
Seawall is expanded upon, including use of timber, concrete bulklheads/seawall and quarry-stone revetments. Construction costs over $5 million for the island by the late 1980s.
September 1979
Hurricane David causes extensive damage to seawall. Seabrook's dry beach areas are greatly diminished.
March 1983
First relocation of Capn Sams Inlet back to it's 1963 inlet position.
February 1990
Northern channel is realigned by an ocean-going dredge. Dredge adds wet beach to area between Pelican Watch Villas and Renken Point.
April 1996
Capn Sams Inlet relocated for a second time to it's 1963 location.
1998-2007
Winter sand scraping implemented to accelerate beach restoration.
June 2015
Capn Sams Inlet is relocated for a third time.
2016
Seabrook Island is selected for an ASBPA (American Shore and Beach Preservation Association) "Best Restored Beaches" Award.
October 2024
Sand scraping and seawall repair project.
2028
Proposed year for a fourth Capn Sams Inlet Relocation.
Seawall Construction
Shore protection sandbags near the Beach Club in 1974
To combat beach erosion, seawall construction was used to protect Seabrook's coast throughout the 1970s and early 1980s. Primary measures implemented include sandbags, quarry stone groins, sandbag revetments, concrete sheet-pile bulkheads and quarry stone revetments. The last seawall structure was built in the early 1980s around Renken Point (~1800 ft) and near the Pelican Watch Villas (~900 ft). Since then, SIPOA has switched to soft-engineering solutions, and seawalls are maintained by individual property owners.
Seawall failure after Hurricane David 1979
In September of 1979, Hurricane David hit the Island and caused severe damage to the seawall around the Beach Club and Renken Point. Major repairs were made to the seawalls at these locations. In the 1980s, seawall collapse occured due to beach erosion, and was later repaired.
Seawall collaspe in 1983 near Beach Court
Since the 1970's, Seabrook Island has installed around 8800 linear feet of seawall. Since 1983, soft engineering solutions have buried all but 2500 linear feet of seawall. Seawall maintenance and repair projects were completed in 2007 and 2024.
Seawall projects since the 1970s
Beach Scraping
Sand scraping is the movement of sand from the intertidal zone to the beach dunes. Beach scraping is done by mechanical means, usually by heavy equipment. This technique can increase the volume of sand on the beach, decreasing short-term erosion. This is a short-term mitigation technique and needs to be repeated and well maintained. Beach scraping is a good short-term solution with a comparitively low cost and low ecological impact.
Seabrook Island has had 10 sand scraping projects in the past. Each project varied in volume of sand moved, sand source and placement area. Cost of beach scraping projects varied based on location and quanitity moved, but typically ranged from $80,000 to $300,000.
October 1982
Volume: 70000 cy Source: Intertidal Bars Placement Area: Beach 17-21
Purpose: Beach build-up
March/April 1983
Volume: 230000 cy Source: Abandoned Inlet Sholes Placement Area: North Beach 20-24
Purpose: Beach build-up
April/May 1996
Volume: 45000 cy Source: Abandoned Inlet Sholes Placement Area: Closure Dike 31-34
Purpose: Capn Sams Inlet closure
February/April 1997
Volume: 75560 cy Source: North Beach Placement Area: Renken Point 18-21
Purpose: Beach build-up
February 1998
Volume: 80000 cy Source: North Beach- Inlet Sholes Placement Area: Outer Dike 30-36
Purpose: Dune nourishment
December/January 1999-2000
Volume: 60000 cy Source: North Beach- Inlet Sholes Placement Area: Build-up Beach 25-33
Purpose: Dune nourishment
January 2002
Volume: 65000 cy Source: North Beach- Inlet Sholes Placement Area: South Beach 13-18
Purpose: Beach build-up
January 2003
Volume: 65000 cy Source: North Beach- Inlet Sholes Placement Area: South Beach 13-18
Purpose: Beach build-up
January/February 2005
Volume: 93100 cy Source: North Beach- Inlet Sholes Placement Area: South Beach 12-18
Purpose: Beach build-up
December/February 2006-2007
Volume: 70997 cy Source: North Beach- Inlet Sholes Placement Area: South Beach 12-18
Purpose: Beach build-up
October 2024
Volume: 150000 cy Source: North Beach Placement Area: South Beach
Purpose: Beach build-up
Dredging
1989 Plan of reallignment of the north inlet
Dredging is the removal of sediment from the bottom of water bodies. Over time, sediment naturally settles, decreasing the depth of water bodies. Often, sediment in the ocean is removed and added to the beach.
In 1990, the northern inlet was realligned by ocean dredging. The ocean-going dredge built a parallel channel 600 feet seaward while filling an exsisting channel along the seawall. This project added 650000 cubic yards of sand to the beach between Pelican Watch Villas and Renken Point. The total cost of the dredging project was $1.6 million.
Start of dredging operations at Renken Point in 1990
The 1990 project was the first nourishment project in South Carolina to use an ocean-certified hydraulic dredge. Since 1990, over twice the amount of sand moved has natually collected in the project area, offsetting the natural encroachment rates. Dredging this area allowed the formation of a wider dry beach and a protective dune along a major portion of the beach. No more dredging operations have been required since 1990.
Capn Sams Inlet Relocation Project
Capn Sams Inlet currently migrates 150 to 300 feet per a year. Sand gets entrapped in the inlet causing beach erosion. Relocating the inlet would allow sand to settle along Seabrook Island's beaches. Capn Sams Inlet has been relocated three times; 1983, 1996, and 2015. The relocation project has a 12-15 year design life.
1983
In February of 1983, Capn Sams Inlet was relocated ~1.5 miles to it's original 1963 location. The new inlet was excavated as an enclosed basin, and formed by breaching an outer derm. The abandoned inlet was enclosed during low tide by bulldozers filling it with surplus sand on either side. The project costed approximately $475,000, significantly more cost effective per cubic yard of sand than other beach renourishment methods.
Relocation of the inlet in 1983 to it's 1963 location, from point B to point A.
"The project was both environmentally sensitive and cost effective, indicating the benefits of combining fundamental research on coastal processes with coastal engineering practices" - National Academy of Sciences (1994)
Result from the 1983 relocation project
1996
Historical Inlet Locations
Capn Sams Inlet was relocated ~4000 ft in 1996. This relocation restored >80% of Seabrook Island's shoreline, a gain of nearly 2 million cubic yards of sand. It buried the seawall, expanded the beach, dunes, and salt marsh without using any physical structures. This project was not a permenant solution and further inlet relocation projects were planned for the future. The project's total construction costs was $536,000.
2015
Capn Sams inlet was relocated ~3000 ft northeast from its original location. Excavation was similar to the previous two projects. The 2015 inlet relocation was completed in record time and with minimal disruption to the project area. Around 140000 cubic yards were excavated and 165000 cubic yards were used to create the closure dike. Total construction cost was $930,500.
January 2015 and July 2015
January 2015 and July 2015
Capn Sams Inlet Relocation Project (2015)
ASBPA "Best Restored Beaches" Award
On May 23rd, 2016, the American Shore and Beach Restoration Association announced the Seabrook Island was a winner of it's 2016 "Best Restored Beach" Award for 2016.
“ASBPA created the Best Restored Beach award as a way of highlighting the value of America’s restored beaches,” said Tony Pratt, ASBPA president and administrator of the Shoreline and Waterway Management Section within the Delaware Department of Natural Resources and Environmental Control. “As Americans flock to our coastline during the upcoming beach season, most don’t even realize they may be enjoying a restored beach.”
To enter the Best Restored Beach competition, coastal communities nominated their projects for consideration, and an independent panel of coastal managers and scientists selected the winners. Judging was based on three criteria: the economic and ecological benefits the beach brings to its community; the short- and long-term success of the restoration project; and the challenges each community overcame during the course of the project.
A complete list of award-winning beaches, and more information about beach restoration and ASBPA, is available online at www.asbpa.org .
Acknowledgements
This storymap was prepared using data and reports from Research Planning Institute, Inc. (1978-1983) and Coastal Science & Engineering, Inc. (1983-Present). The projects were also completed in close cordination with the SIPOA Environmental Commitee. Photos were provided by the Seabrook Island Property Owners Association and Coastal Science & Engineering Inc. Video was provided by Steven Traynum at Coastal Science & Engineering, Inc.
References
CSE. 2015. Capn Sams Inlet Relocation, Seabrook Island, South Carolina. Final Report to Seabrook Island POA; CSE, Columbia, SC, 61 pp + appendices.
CSE. 2016. Capn Sams Inlet Relocation, Seabrook Island, South Carolina. Monitoring Report to Seabrook Island POA; CSE, Columbia, SC, 77 pp + appendices.
NRC. 1994. Restoring and Protecting Marine Habitat, Inlet Engineering Seabrook Island at South Carolina. 143-144 pg.
Town of Seabrook Island. 2019. Comprehensive Beach Management Plan; Seabrook Island, SC, 1-164 pg.
YouTube. (2019). Capn Sams Inlet Relocation Project. YouTube. Retrieved July 14, 2022, from https://www.youtube.com/watch?v=19xt39yjqPw.