
TH 610 & East River Road
Scroll down for more information!
Welcome to the online site for the Trunk Highway (TH) 610 & East River Road Intersection Improvement project! We created this interactive resource to provide project information and updates.
Continue scrolling down the page or use the menu at the top to jump to specific topics.
Visit the "Project Timeline" section for recently updated information on the progress made in 2024. Visit the the "Current Recommended Layout" section for the most up-to-date design.
Project Overview
Currently, only westbound on-ramps and eastbound off-ramps to and from TH 610 exist at both East River Road and Coon Rapids Boulevard. Several plans for improvements are currently being considered. Although no formal plans have been approved, in 2020, the proposed project received $1.5 million in state bonding funds to complete preliminary design work and environmental review. Your input is an important part of this preliminary work.
Purpose & Need:
The purpose of the TH 610 and East River Road Project is to address limited access to and from TH 610 to support existing and future land uses in Coon Rapids, improve safety and emergency response access, and increase the functionality of TH 610 as an important route in the statewide transportation system.
The City of Coon Rapids has identified the following transportation problems that need to be addressed by the TH 610 and East River Road Project:
Limited Access:
- There is inadequate access to TH 610 to and from the east in southern Coon Rapids between TH 10 and the Mississippi River.
- As detailed in the map below, trips destined to land uses at TH 610 and East River Road or Coon Rapids Boulevard require a circuitous trip that uses TH 10 and Foley Boulevard. This additional traffic contributes to poor operations at the TH 10/Foley Boulevard interchange. Traffic queues often extend from Foley Boulevard to TH 10 during peak travel hours.
- Approximately 15% of freight trips destined to the area are from TH 610 to the east. The lack of access to and from the east means that these freight trips must use either Foley Boulevard or another route to access the East River Road/Coon Rapids Boulevard area.
Existing Eastbound Access to TH 610
Safety and Emergency Response Access:
- The lack of direct access in this area creates a challenge for emergency response teams from the City of Coon Rapids, especially in the area of eastbound 610 between the river and University Avenue.
- Many times, police and fire personnel must ask the City of Brooklyn Park for immediate assistance due to their proximity to existing TH 610 access.
- The number of times the Fire/EMS teams responded to this area of TH 610 has had an average annual increase of 35% from 2016-2019. These numbers do not include State Patrol data.
Increased Functionality:
- Westbound TH 610 motorists destined to the area that miss the exit to TH 10 and Foley Boulevard must travel across the Mississippi River to Brooklyn Park and turn around at either TH 610/Noble Parkway or TH 252/85th Avenue. This results in an out-of-direction trip of more than 5 miles.
- Segments of the current access routes travel through residential neighborhoods on Foley Boulevard and University Avenue Northeast.
Project Timeline:
Evaluation Criteria
Evaluation criteria are measurable goals and objectives used to study solutions and determine how each proposed improvement solves the identified problems. Potential evaluation criteria for TH 610 and East River Road include:
Project Timeline
2011
The Coon Rapids City Council directed staff to investigate better access to and from the east at TH 610 in the area around Coon Rapids Boulevard. Many of the surrounding properties were interested in potential redevelopment, and improved access to/from the east was a critical economic development concern. Additionally, the industrial/commercial property owners in the area bounded by Coon Rapids Boulevard, TH 47, 85th Avenue NW and the BNSF Railroad tracks also expressed concerns with current access limitations to TH 610. In the fall of 2011, the City hired a consultant to identify potential concepts to provide better access. The preferred concept was a buttonhook for the westbound ramps connecting into Foley Boulevard.
January 2014
City, County, and Interchange Committee members from MnDOT and the Metropolitan Council met several times to discuss the proposed project. Ultimately, the Committee sent a letter stating the project did not meet the qualifying criteria. In general, the City and County wanted to continue pursuit of the interchange, but funding constraints limited further pursuit of the project at that time.
June 2018
Property required for the proposed TH 610/Coon Rapids Boulevard westbound buttonhook became available on the real estate market. The City purchased it in June 2018, primarily for the interchange. Since 2012, Anoka County, in partnership with the City, pursued funding for the Foley Railroad Grade-Separation project. The project has now received federal funding and is currently in
the construction phase.
September 5, 2019
The Minnesota Department of Transportation agreed that certain design standards for the proposed access interchange at East River Road meet the criteria required by the Interchange Review Committee. Read the letter from MnDOT here.
2020
The City of Coon Rapids and Anoka County requested $1.5 million in the 2020 legislative session for the preliminary design and environmental documentation of a full access interchange for TH 610 at East River Road. Funds were received in January 2021. The Coon Rapids City Council approved an application for a Roadway Expansion Grant through the Metropolitan Council’s 2020 Regional Solicitation program to the Transportation Advisory Board. Future next steps on the TH 610 project will be dependent upon if funds are received through the state bonding funding or this regional solicitation program grant. The City was unsuccessful in securing this funding.
2021
On May 4, 2021, the City Council awarded a consulting contract to begin the environmental documentation and design phase of the TH 610/East River Road full access interchange, and work began immediately. The design process will last approximately two years, but the City is striving for a MnDOT-approved layout in Fall 2022 in order to begin developing a funding package for construction. From June 14 through July 2, the City’s engineering consultant collected data needed for design and alternative development. Work included survey crews, UAV (drone) flights, and wetland delineations. The first public open house was conducted virtually on July 30 to review project alternatives. Open house #2 was held in person on August 31, 2021. Three alternative designs were presented and discussed. The project team performed a technical review of each alternative and comments received to determine which layouts were constructible.
December – February 2022
Open house #3 was held in person on December 15, 2021. Two refined alternatives were presented for public review. On January 11, 2022, a work session was conducted with local elected officials to discuss progress to date and provide input on a preferred alternative. On February 24, 2022, open house #4 was held virtually. The preferred alternative was presented for public review and comment.
April – May 2022
The project team submitted an application requesting federal funds for the preferred alternative through the Metropolitan Council's 2022 Regional Solicitation program. The City was unsuccessful in securing this funding. Coordination with the railroad for bridge widening began in April 2022. In May, the preferred alternative was submitted to MnDOT and Anoka County for agency review and acceptance.
June-August 2022
Value Engineering (VE) study of the preferred alternative was performed. A link to the report can be found here. The preferred alternative remained substantially similar and was submitted in August 2022 to MnDOT for official review and approval. Geotechnical investigations for structures and roadway embankments began and is currently underway.
October 2022
The fifth open house was held on October 27, 2022. The preferred alternative was presented to the public and feedback was collected. Field monitoring for the noise analysis began in October as well. Data collected from this will inform the environmental document and final design.
December 2022
MnDOT approved the preferred alternative (illustrated below), and it is now referred to as the Staff Approved Layout.
January - March 2023
The project team continued coordination with BNSF Railroad to address the project's impacts on the existing bridges in the project area. After a final review of the preferred alternative, BNSF Railroad determined that the existing TH 610 bridges do not meet clearance requirements and still have an active service life of more than 50 years. This decision changed the project’s evaluation criteria and new alternatives were required.
April – September 2023
The project team developed new geometric alternatives on the south side of TH 610 to eliminate any impact to BNSF Railroad right-of-way or the existing TH 610 bridges over BNSF Railroad. These alternatives were submitted to MnDOT for review. This process led to the development of a recommended alternative. This alternative is currently being evaluated against the previous design, which included the full replacement of the bridges over the BNSF Railroad tracks. In June, the City submitted a request for $23,000,000 through the 2024 Capital Bond Program for construction. The request will be reviewed during the next legislative session. The 2023 legislative session awarded the City $1,000,000 through the 2023 Local Road Improvement Program (LRIP) Bond program to further project development. In September, the City submitted a request for $10,800,000 through the Minnesota Highway Freight Program for construction. Awards will be announced in early 2024.
October – December 2023
The recommended layout was presented to the City Council for review. The project team provided updates to the public during a public open house meeting on December 1, 2023 to discuss the current recommended layout. In December, the City applied for construction grant funding through the 2024 Regional Solicitation. Awards will be announced in late summer 2024.
January – March 2024
The project team continued development of the environmental documentation, and started final design of the Staff Approved Layout, and conducted remaining geotechnical borings for the bridge and retaining wall structures. The environmental documentation work included development of an Alternatives Analysis Report, initial noise modeling, and coordination with stakeholder agencies.
March - June 2024
After some additional alternatives analysis, the project team developed a new, preferred recommended layout. To view the current recommend layout, click here . The project received $10,800,000 from the Minnesota Highway Freight Program.
July 2024
30% construction plans were completed.
September 2024
The project was recommended to receive $10,000,000 from the Metropolitan Council Regional Solicitation grant. Official notification will be received this fall.
Looking Ahead:
Winter 2025
60% construction plans complete.
Fall 2025
100% construction plans complete.
Future
Construction will not occur until the project has received complete funding.
Existing Conditions
Tour the project site: Use the Google Streetview image below to explore the existing conditions along TH 610 & East River Road.
Google Street View Map of Project Area *Click directly inside the image to navigate
North of the project area is the CSAH 11 (Foley Boulevard) BNSF Railway Grade Separation project, which is now complete.
Community Engagement Summary
Virtual Open House #1 Summary:
A virtual open house was launched on July 30, 2021 as part of the community engagement efforts for the Trunk Highway 610 & East River Road Access Interchange project. An interactive, online platform was used to share project background information and included a survey for community feedback. The survey was open from July 30, 2021 – August 31, 2021.
In-Person Open House #2 Summary:
The following items were presented at the August 31, 2021 Open House. High level alternatives were presented to solicit input on the project and to help guide the process moving forward. All comments received during the engagement process will be utilized to help refine the alternatives and to assess them against the Evaluation Criteria (presented above). The next steps will include refining the alternatives, evaluating potential impacts, and presenting a preferred alternative. These items will be presented at a future Open House, planned for this winter, to solicit input.
Click the button below to download higher resolution boards:
In-Person Open House #3 Summary:
The December 15, 2021, open house included a summary of project's evolution to date. Two refined alternatives were presented and discussed to solicit additional input. All public engagement comments received throughout the project will be included in the decision-making process to select a preferred alternative. Local officials will be reviewing all pertinent information and will provide their feedback in the near future. Following the selection of the preferred alternative, environmental documentation and stakeholder review will occur as the project moves into final design. Additional details on the project will be added to the website as they become available, and notifications will be sent to everyone who has signed up to receive project updates. It is anticipated there will be another Open House in the spring of 2022.
Click the button below to download higher resolution boards:
Virtual Open House #4 Summary:
A virtual open house was launched on February 15, 2022, as part of the community engagement efforts for the Trunk Highway 610 & East River Road Access Interchange project. An interactive, online platform was used to share the preferred alternative for the interchange. An interactive map and survey were used to solicit feedback.
The following is a summary of all engagement to date.
Summary of community engagement
For high resolution images, click the link below:
In-Person Open House #5 Summary:
The fifth open house was held in person on October 27, 2022. Materials presented included a summary of the project evolution to date and the preferred alternative. Feedback included an overall support of the preferred alternative as well as a desire to minimize impacts to the surrounding neighborhoods.
In-Person Open House #6 Summary:
The sixth and final open house was held in person on December 1, 2023. The current recommended layout was presented along with the project timeline and decision matrix. Feedback from participants showed overall support for the project. Some cited concerns about potential traffic increases and noise impacts. Participants were informed about the noise analysis process.
Click the button below to download the boards presented at the open house:
Current Recommended Layout
Below represents the current recommended layout for the proposed interchange. This layout was developed from feedback from the community, a value engineering study, and engineering limitations and opportunities. To interact with the slider, select the arrows and move them to the right to see the existing conditions and to the left to see the preferred alternative.
Contact Us
Questions can be directed to Tim Himmer, Public Works Director
Email: thimmer@coonrapidsmn.gov
Phone: 763-767-6494