
Riverfront Parks
Priority River Vision Plans
These Riverfront Park Projects are all major multi-million dollar projects intended to connect the community to the river in a multitude of ways and provide for river restoration.
Centennial-Rainey Park
Implementation Plan - RiverVision simple map
Short term project
Timeframe: <5 years; #1 Priority
Status: 30% design completed. 60% design will be completed in fall 2021
Location: At the base of City Creek on both sides of the Portneuf River
Project lead: City of Pocatello (design); Sagebrush Steppe Land Trust (fundraising).


Oxbow Park
Implementation Plan - RiverVision simple map
Long term project
Timeframe: >5 years;
Status: Preliminary concept phase
Location: East of the railroad tracks from the Highway Ponds near Century High School north to S. 2nd Ave.
Project lead: City of Pocatello
Center Street
Project location
Long term project
Timeframe: >5 years;
Status: Concept phase
Location: Center Street at the Portneuf River, just west of the library and Simplot Square.
Project lead: Historic Downtown Pocatello
Memorial Park
Implementation Plan - RiverVision simple map
Long term project
Timeframe: >5 years
Status: Concept developed
Location: Memorial Park (Lander to Wyeth)
Project Lead: TBD
Memorial to Raymond
Memorial to Raymond Project Location
Long term project
Timeframe: >5 years
Status: Preliminary concept
Location: Concrete channel between Memorial and Raymond Parks (Wyeth to Custer)
Project Lead: TBD
Raymond Park
Raymond Park location
Long term project
Timeframe: >5 years
Status: Concept developed
Location: Raymond Park (between Custer & Carson Streets)
Project Lead: TBD
Sacajawea Park location
Sacajawea Park
Long term project
Timeframe: >5 years
Status: No design work done
Location: Sacajawea Park (Carson Street to Kraft Road)
Project Lead: TBD
Pacific Recycling/Kraft Road location
Pacific Recycling/Kraft Rd. Park
Long term project
Timeframe: >5 years
Status: Student concepts developed
Location: Pacific Recycling Trailhead and across the river at N. Main and Kraft Road.
Project Lead: TBD
Kraft to Batiste - Restoration and Pathways
Implementation Plan - SimpleMap
Longterm
Timeframe: TBD
Status: Preliminary concept only
Cost: TBD