Story logo

Sewer Conveyance Project Construction Map for 2024/2025

Know the Route; Plan Your Commute

Visit Engage Comox Valley Sewer Conveyance Project website for the 2025 traffic management plan.

1

Beaufort Avenue from Jane Place to Stewart Street

COMPLETE

BC Transit construction-related route changes in effect April 1.

2

Stewart Street South of Comox Ave.

COMPLETE

BC Transit construction-related route changes come into effect April 1st.

Check BC Transit for rider details.

3

Comox Avenue & Stewart Street Intersection CLOSED July 11 & 12 For Paving Work

COMPLETE

The intersection of Comox Avenue and Stewart Street in the Town of Comox will be closed July 11 and July 12, 2024, 7:00 am – 7:00 pm for paving work.

The intersection will be closed to all vehicles except for emergency vehicles.

Please avoid this intersection for the duration of the closure and use signed detour routes.

Pedestrian access to residences will be maintained.

Work will continue up Stewart Street. Properties on Stewart Street, Alder Avenue and Arbutus Avenue will receive notices from Wacor about when residents can expect limited access due to paving.

Please view BC Transit website for up-to-date information on detours due to construction.  https://alerts.bctransit.com/ 

4

Comox Avenue and Stewart Street Intersection

COMPLETE

Work continues at the Stewart Street and Comox Road intersection. Wacor is replacing some storm sewer within the intersection that was identified for replacement as part of the construction project. Wacor is also installing curb and gutter along Stewart and preparing paving along Stewart

 

This work will impact traffic and will require single-lane alternating traffic along Comox Avenue, beginning the week of June 24, 2024.

It may also require detours near and around this intersection which may move depending on the work being completed. Please allow extra time for travel and follow all posted signage and detours.

Effective May 1 until further notified BC Transit Comox Exchange turnaround will be via Pritchard Road while work proceeds along Stewart Street.

5

Stewart Street between Comox Avenue and Balmoral Avenue

COMPLETE

Approximate start date: May 1

Duration: May -July

-Full road closures for through traffic. -Notice will be given by the contractor 14 days in advance of restrictions to driveways along Stewart Street. -Access will be provided at all times to all multi-family complexes, as well as residences on Alder Avenue and Arbutus Avenue. -Pedestrian access at all times. -Temporary closure to tennis courts parking lot along Stewart St. -Prior to construction, details regarding garbage and recycling collection will be provided by the contractor. -Emergency vehicle access unrestricted. -Effective May 1 until further notified BC Transit Comox Exchange turnaround will be via Pritchard Rd.

6

Balmoral Avenue: Stewart St. to Pritchard Rd.

Sewer Forcemain - COMPLETE Storm Drain, Curbs & Paving - Ongoing

Approximate Start Date: May 27.

Duration: June - July - Forcemain Work July - Aug: Town of Comox Infrastructure Upgrades August - September: Paving and Curb Forming

-Traffic restrictions will be in place. Check the  Project News  section on the project website for bulletins and announcements.

-Full closures; single-lane westbound direction only after construction hours.

-Vehicle access to multi-family residential complex at all times.

-Pedestrian access to residences and businesses at all times.

-Emergency vehicles unrestricted.

-Full details on traffic plan shared 2 - 4 weeks in advance of construction.

-Town of Comox surface works: South side pedestrian walkway along Balmoral Avenue between Stewart and Pritchard streets.

-BC Transit schedule changes will be in effect as of April 1st once construction begins.

Check BC Transit for rider details.

7

Air Release Valve Kiosk

As part of the sewage conveyance forcemain, six air release valves will be installed within the Town of Comox.

Air release valves are critical on forcemains to prevent airlocks during operation. The kiosks are sealed units, and any air released is directed back into the gravity sewage collection system preventing any odour concern.

The kiosks measure 1.67m high, 1.24m wide, and 0.9m deep (5’6’’ x 4’ x 3’).

After construction, the CVRD will work with the Town of Comox on custom wraps to minimize visual impacts.

8

Balmoral Avenue and Pritchard Road Intersection

COMPLETE

Intersection CLOSED July 15-17 for Sewer Forcemain Installation

-The intersection will be closed 24 hrs day to all through traffic in all directions. -Emergency vehicle access unrestricted. -Pedestrian access at all times. -Please view BC Transit website for up-to-date information on detours due to construction.  https://alerts.bctransit.com/ 

9

Balmoral Avenue: Pritchard Rd. to Torrence Rd.

What to Expect

Start Date: July 18, 2024

Duration: July - August: Sewer Forcemain Work September: Town of Comox Infrastructure Upgrades October: Paving and Curb Forming

Construction on Balmoral Ave. east of Pritchard Rd. is began July 18.

Construction will be crossing Donovan Drive August 12, 2024.

Please follow all detour routes. Going to or coming from Goose Spit, please follow the detour of Noel Ave. to Torrence Rd.

Full road closure during construction hours 7 am to 8 pm. Single lane westbound direction only after construction hours.

Vehicle access to Marida Pl. and the multi-family residential complex, Spinnaker West, will be at all times.

Pedestrian access at all times.

Emergency vehicles unrestricted.

BC Transit schedule changes will be in effect as of April 1st once construction begins.

10

Partial Closure Balmoral Ave. August 19- 21 Donovan Dr. to Torrence Rd.

What to Expect: CLOSED 24 HR/DAY

The road closure is required to accommodate the installation of the sewer forcemain pipe in the area of the Brooklyn Creek bridge.

Residents of Balmoral Avenue and emergency services will be provided access.

Please allow extra time for commuting and follow posted detour routes. Please obey speed limits and the directions of the traffic control personnel.

We appreciate the cooperation and support of residents as we work to complete this important project.

11

Air Release Valve Kiosk

As part of the sewage conveyance forcemain, six air release valves will be installed within the Town of Comox.

Air release valves are critical on forcemains to prevent airlocks during operation. The kiosks are sealed units, and any air released is directed back into the gravity sewage collection system preventing any odour concern.

The kiosks measure 1.67m high, 1.24m wide, and 0.9m deep (5’6’’ x 4’ x 3’).

After construction, the CVRD will work with the Town of Comox on custom wraps to minimize visual impacts.

12

Brent Road

What to Expect

When: August 6 - August 29

Full road closure of Brent Rd for through traffic. Local access only. Notice will be given by the contractor in advance of restrictions to driveways. Pedestrian access at all times. Emergency vehicle access unrestricted. Residents with private waste collection, please follow these guidelines:

Clear Labeling: To facilitate smooth handling and return of bins, please ensure that all bins are clearly labeled with your home address.

Placement of Waste Bins: During periods when roads are fully closed, residents are required to place their bins at the end of their driveway 7:00 am on scheduled pickup days.

Collection by Crews: Contractor crews will retrieve the bins and bring them to a central location outside the road closure area (Lazo Rd.) for collection by the waste management trucks.

Return of Bins: Following collection, bins will be returned to their respective driveways by the end of the day.

13

Air Release Valve Kiosk

As part of the sewage conveyance forcemain, air release valves will be installed along the route of the pipe. The kiosk are sealed units, and any air released is directed back into an underground chamber complete with a carbon filter on the lid preventing any odour concern. The installation of the air release valve is a crucial component of the sewer system as they prevent airlocks during operation. This kiosk measures 1.67m high, 1.24m wide and 0.9m deep (5’6’’ x 4’ x 3’). Installation of the kiosk is expected to be in the spring of 2025.

14

Curtis Road Detour

What to Expect

Completed

When: August 8 - August 29

For the duration of the Brent Road Closure, traffic, including Brent Road residents and access to the Comox Valley Water Pollution Control Centre, will be detoured along Curtis Road, through the fire gate and along the maintenance access road.

There will be a temporary increase in traffic on Curtis Road.

Sewage hauling trucks, delivery trucks and local resident traffic will be using Curtis Road as the approved detour route. Traffic control personnel will be positioned on Curtis Road for safety.

Please allow extra time for commuting, follow posted speed limits and obey all the directions of the traffic control personnel.

15

Torrence Road

What to Expect

When: Estimated start, September 3.

Intersection closures is required. Access to Hawkins and Croteau roads maintained at all times.

Pedestrian access to residences and businesses at all times.

Emergency vehicles unrestricted.

BC Transit construction-related route changes come into effect April 1st.

Check BC Transit for rider details.

16

Lazo Marsh Crossing/Knight Road Detour

The dryer season of August and September are advantageous for the construction of the sewer forcemain that will cross over the marsh along Lazo Road.

What to Expect

Brent Rd/Lazo Rd Intersection: August 26 - 28 Lazo Road: August 29 - October 16

Pipe installed within existing roadway.

Rolling one to two block closures; single lane alternating when full closure not required.

Knight Rd detour in effect to ensure access to residences maintained.

17

Air Management Point

At the corner of Beckton Drive and Lazo Road, a piece of critical infrastructure will be installed called the Air Management Point.

Key Points:

-This site includes continuous air release through an activated carbon scrubber, which removes odorous gas to a level of 0.1 parts per million of H 2 S (Hydrogen Sulfide).

-This site includes a fan which will have custom acoustic enclosure to minimize noise, designed to achieve a maximum sound intensity of 45 dB (decibels), similar to the fridge in your house.

-Approximate maintenance schedule: Routine maintenance twice per year, including examination and testing of carbon scrubber. Carbon media within the scrubber will be replaced every two years.

-The infrastructure is recessed into slope to reduce height.

-Concrete fencing will surround the infrastructure to hide and help reduce noise.

-Maintenance access from the new Lazo Mulit-Use Path.

-Installation of the kiosk is expected to be in the spring of 2025.

18

Lazo Road - Torrence Road to Brent Road

What to Expect

Pipe installed within one lane of roadway.

One to two rolling block closures.

Local detours to ensure access to residences maintained.

Full details on traffic plan shared 2 - 4 weeks prior to construction.

19

Air Valve Release Kiosk

Due to topography, air valves required along length of pipe to air to vent in/out during fluctuating flows.

Kiosks will be installed along entire length including along Lazo Rd. The unit being installed at this location is for continuous air intake only. There will be no air discharged and no risk of odour. The installation of the air intake is a crucial component of the sewer system. The kiosk measure 2.3 meters tall x 2.8 meters wide and 1 meter deep. There are two pipes which will protrude from the sides at the top of the kiosk (to intake air only). Installation of the kiosk is expected to be in the spring of 2025.

20

Air Intake Kiosk

Due to topography, air valves required along length of pipe to air to vent in/out during fluctuating flows. Kiosks will be installed along entire length including along Lazo Rd. The unit being installed in this location is for emergency air intake only. The air intake is designed to only operate when there is the risk of negative pressure in the sewer forcemain pipe. There will be no air discharged at this kiosk and no risk of odour. The installation of the air intake is a crucial component of the sewer system. The kiosk measures 4 feet tall x 3 feet wide. Installation of the kiosk is expected to be in the spring of 2025.

21

Comox Pump Station

2025 Construction Project

22

Beaufort Avenue west of Jane Place to Rodello Street

In August 2024, after the BC Long Weekend and Nautical Days activities, construction will begin along the length of Beaufort Ave. from Jane Pl. to Rodello St.

What to Expect

Rolling one to two block closures.

Vehicle access to boat launch and marina maintained between May and October.

Pedestrian traffic maintained to all residences, businesses and public library.

Full details on traffic plan shared 2 - 4 weeks in advance of construction.

Town of Comox surface works between Church and Wilcox streets (see images above).

Transit routes to be relocated to Comox Ave.

23

Air Release Valve Kiosk

As part of the sewage conveyance forcemain, air release valves will be installed within the Town of Comox.

Air release valves are critical on forcemains to prevent airlocks during operation. The kiosks are sealed units, and any air released is directed back into the gravity sewage collection system preventing any odour concern.

The kiosks measure 1.67m high, 1.24m wide, and 0.9m deep (5’6’’ x 4’ x 3’).

After construction, the CVRD will work with the Town of Comox on custom wraps to minimize visual impacts.

24

Air Release Valve Kiosk

As part of the sewage conveyance forcemain, air release valves will be installed within the Town of Comox.

Air release valves are critical on forcemains to prevent airlocks during operation. The kiosks are sealed units, and any air released is directed back into the gravity sewage collection system preventing any odour concern.

The kiosks measure 1.67m high, 1.24m wide, and 0.9m deep (5’6’’ x 4’ x 3’).

After construction, the CVRD will work with the Town of Comox on custom wraps to minimize visual impacts.

25

Air Release Valve Kiosk

As part of the sewage conveyance forcemain, air release valves will be installed within the Town of Comox.

Air release valves are critical on forcemains to prevent airlocks during operation. The kiosks are sealed units, and any air released is directed back into the gravity sewage collection system preventing any odour concern.

The kiosks measure 1.67m high, 1.24m wide, and 0.9m deep (5’6’’ x 4’ x 3’).

After construction, the CVRD will work with the Town of Comox on custom wraps to minimize visual impacts.

26

Rodello Street Roundabout

As part of the project there are several roadway improvements that are also planned, which are intended to greatly improve traffic circulation in the Town of Comox. These upgrades include a new roundabout located at the intersection of Comox Ave. and Rodello St. within the Town of Comox.

2025 Construction Project

27

Air Release Valve Kiosk

As part of the sewage conveyance forcemain, six air release valves will be installed within the Town of Comox.

Air release valves are critical on forcemains to prevent airlocks during operation. The kiosks are sealed units, and any air released is directed back into the gravity sewage collection system preventing any odour concern.

The kiosks measure 1.67m high, 1.24m wide, and 0.9m deep (5’6’’ x 4’ x 3’).

After construction, the CVRD will work with the Town of Comox on custom wraps to minimize visual impacts.

28

Air Valve Release Kiosk

As part of the sewage conveyance forcemain, six air release valves will be installed within the Town of Comox.

Air release valves are critical on forcemains to prevent airlocks during operation. The kiosks are sealed units, and any air released is directed back into the gravity sewage collection system preventing any odour concern.

The kiosks measure 1.67m high, 2.08 m wide, and 0.9m deep (5’6’’ x 6'8" x 3’).

After construction, the CVRD will work with the Town of Comox on custom wraps to minimize visual impacts.

29

Glacier View Drive Roundabout

As part of the project there are several roadway improvements that are also planned, which are intended to greatly improve traffic circulation in the Town of Comox. These upgrades include a new roundabout located at the intersection of Glacier View Dr. and Comox Ave.

2025 Construction Project

30

New Courtenay Pump Station (CPS)

Starting June 1, 2024, work will begin at the site of the new CPS.

What to Expect

Work will be off Comox Rd. Minimal traffic disruptions.

Watch for traffic flaggers and temporary pedestrian crossing lights on location.

31

Comox Road 2025 Construction

Commencing January 2025 for approximately 9 months (fall 2025) sections of Comox Rd. will be worked on.

What to Expect

Unidirectional traffic flow (westbound only) will be in effect.

Traffic Management Strategy planning spring 2024 for June public consultation process. Details will be posted on the project page under the  News Section  

Pre-construction Public Information Sessions fall 2025.

What we are building

Comox Valley Sewer Conveyance Project

The purple line represents the new sewer forcemain route inland. The Comox Valley Regional District is also constructing a new seismically resilient Courtenay Pump Station and upgrading the

The Comox Valley Sewer Conveyance Project will route sewer pipes from the foreshore further inland where they will no longer be vulnerable to damage by waves, rocks and logs. This project is key to protecting the coastline, resolving environmental risk and preparing for future growth. This is a significant and complex infrastructure undertaking that starts at a new Courtenay Pump Station and moves through K’ómoks land, downtown core of the Town of Comox and easterly along Lazo Road to the Comox Valley Water Pollution Control Centre (Sewage Treatment Plant) on Brent Road. The CVRD is working with many jurisdictions and partners to deliver this project smoothly and efficiently and to minimize impacts where we can.

The project will be constructed over a 30-month period, approximately, with the first phase involving works in the Town of Comox and sections of Electoral Area B throughout 2024. The second phase of the project will commence in 2025 and entails construction along Comox Road that passes along K’ómoks IR1 to the top of Comox Hill and along Comox Avenue to Rodello St. Upgrades to the K’ómoks and Town of Comox pump stations will also take place in 2025.

Work will be divided into four construction zones in 2024, each with distinct traffic impacts. Within the Town of Comox, work will be completed in three phases and will require sections of roads to be impacted more than once:

  • Storm and watermain replacement
  • Sewer forcemain installation
  • Surface improvements, paving and roundabouts (extending into 2025 and 2026)

Details pertaining to the 2025 construction schedule and traffic plan are under development and will be presented to the community in fall 2024 to prepare residents, businesses and commuters in advance of construction.

Resources

Send us your questions?

The purple line represents the new sewer forcemain route inland. The Comox Valley Regional District is also constructing a new seismically resilient Courtenay Pump Station and upgrading the