Thank you for visiting the Franklin Road, McDermott Road to Black Cat Road Open House. Here you will find information about the project. At the end, you will be able to provide feedback on the project.

Please continue scrolling down to browse through the full content of the website or toggle to different sections using the navigation bar above.

If you need printed materials mailed to you or need to make other arrangements to answer your questions, please call 208-387-6100 | TTY 1-800-377-3529 and we will be happy to help you.

This virtual open house will be open through January 25th.

Project Purpose

  • Improve motorist, pedestrian, and bicyclist safety.
  • Accommodate future traffic volumes.

Project Description

Widen Franklin Road, between McDermott Road and Black Cat Road, to two travel lanes in each direction with a continuous center turn lane and medians where appropriate.

Raised medians will be located within the center lane in areas where they do not restrict access from public streets and/or driveways.

Center medians are a raised portion of the roadway separating opposing directions of traffic and can provide traffic calming, aesthetic benefits, access management, and increase overall safety.


Renderings are for illustrative purposes only

Construct a 10-foot, multi-use pathway on both sides of Franklin Road.


Renderings are for illustrative purposes only

Improve and construct headwalls and irrigation pipes at the crossings of Perkins and Rosenlof Drains.

Improve the intersection of Franklin Road and McDermott Road by adding additional through lanes and turn lanes and installing a signal to help with the predicted increased traffic volumes that will come as a result of the  Idaho Transportation Department’s State Highway 16 improvements project. 

Note: Click and drag the slider bar right and left to compare the proposed design to the existing roadway.

Project Considerations


Renderings are for illustrative purposes only

Multi-Use Pathways

ACHD‘s Roadways to Bikeways Master Plan calls for more robust bike facilities along this type of roadway.

Multi-Use Pathways:

  • Are two-way facilities meant to accommodate both pedestrians and bicyclists of a wide range of ages and abilities.
  • Provide more space between motorists and those walking and biking, which increases safety.
  • Are used on roads with higher speeds and traffic volumes.

Other Projects Planned in the Area

ACHD has many projects planned for this area over the next five years.

To learn more about the projects on the map go to  ACHD's interactive Integrated Five-Year Work Plan map.  

Project Timeline

2023

Design started

January 2024 - We Are Here

Public input opportunity #1

Winter 2024

Revise design based on public feedback

Spring 2024

Public input opportunity #2

Late 2024/2025

Begin purchasing property necessary for the project

2028/2029

Start construction

What do you think?

Thank you for taking the time to review information about the Franklin Road, McDermott Road to Black Cat Road Project. The next step is to review the design and return to the project webpage to tell us what you think.

Survey

While your comments are always welcome, they can be best used if received by January 25, 2024.

After the comment period closes, ACHD will review and address comments received from the public.


Contact Us

Reid Selmer, ACHD Project Manager

(208) 387-6249

projects@achdidaho.org