Quiota Creek Fish Passage Improvement Projects

Cachuma Operation and Maintenance Board (COMB)

Powered by Esri

Tributaries of the Lower Santa Ynez River and Quiota Creek Fish Passage Improvement Projects (zoom in and click)

Powered by Esri
1

Quiota Creek Crossing 6 (2008)

Treatment: 48-foot prefabricated Contech bottomless-arched culvert bridge

Design: HDR Fisheries Design Center

Funding: $371,000 California Coastal Conservancy; $506,627 Cachuma Project Member Agencies

2

Quiota Creek Crossing 2 (2011)

Treatment: 60-foot prefabricated Contech bottomless-arched culvert bridge

Design: HDR Fisheries Design Center

Funding: $700,528 CDFW-FRGP; $117,654 Cachuma Project Member Agencies

3

Quiota Creek Crossing 7 (2012)

Treatment: 60-foot prefabricated Contech bottomless-arched culvert bridge

Design: HDR Fisheries Design Center

Funding: $400,108 CDFW-FRGP; $357,018 WCB; $137,975 Cachuma Project Member Agencies

4

Quiota Creek Crossing 1 (2013)

Treatment: 60-foot prefabricated Contech bottomless-arched culvert bridge

Design: HDR Fisheries Design Center

Funding: $521,141 CDFW-FRGP; $150,000 WCB; $228,681 Cachuma Project Member Agencies

5

Quiota Creek Crossing 3 (2015)

Treatment: 53-foot prefabricated Contech bottomless-arched culvert bridge

Design: HDR Fisheries Design Center

Funding: $705,205 CDFW-FRGP; $219,863 Cachuma Project Member Agencies

6

Quiota Creek Crossing 0A (2016)

Treatment: 55-foot prefabricated Contech bottomless-arched culvert bridge

Design: HDR Fisheries Design Center

Funding: $604,637 CDFW-FRGP; $50,000 Landowner; $133,801 Cachuma Project Member Agencies

7

Quiota Creek Crossing 4 (2016)

Treatment: 54-foot prefabricated Contech bottomless-arched culvert bridge

Design: HDR Fisheries Design Center

Funding: $937,838 CDFW-FRGP; $181,034 Cachuma Project Member Agencies

8

Quiota Creek Crossing 5 (2018)

Treatment: 59-foot prefabricated Contech bottomless-arched culvert bridge

Design: HDR Fisheries Design Center

Funding: $893,287 CDFW-FRGP; $234,450 Cachuma Project Member Agencies

9

Quiota Creek Crossing 9 (2018)

Treatment: 60-foot prefabricated Contech bottomless-arched culvert bridge

Design: HDR Fisheries Design Center

Funding: $993,121 CDFW-FRGP; $217,852 Cachuma Project Member Agencies

10

Quiota Creek Crossing 8 (2020)

Treatment: 54-foot prefabricated Contech bottomless-arched culvert bridge

Design: HDR Fisheries Design Center

Funding: $1,010,700 CDFW-FRGP; $174,129 Cachuma Project Member Agencies